United States › Grid › Interconnection queues › Colorado
SOLAR · WESTSolar project GI-DISIS-2021-06, Montezuma County
Solar project GI-DISIS-2021-06, Montezuma County is a 140 MW solar request suspended in the West interconnection queue, in Montezuma County, Colorado, connecting to Tri-State Generation and Transmission Association.
- PlanningQueued May 2021 (current stage)
- ConsentedOct 2025 (not yet reached)
- Construction (not yet reached)
- OperatingTarget Oct 2025 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- GI-DISIS-2021-06
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Tri-State Generation and Transmission Association
- Connection point (POI)
- Main Switch 115kV Substation
- Location
- Montezuma County, Colorado
- Technology
- Solar: 140 MW
- Total requested
- 140 MW
- Service type
- Network resource (NRIS)
- Study phase
- Suspended LGIA
- Queue status
- Suspended
- Entered queue
- 27 May 2021
- Agreement signed
- 6 October 2025
- Proposed online date
- October 2025
Location
Marker shows the centre of Montezuma County; the queue data does not give exact sites.
Other requests in Montezuma County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem