OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2019 requests) โ page 8
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Solar project 358, Butler County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1380, Beauregard Parish County Solar |
200 MW | Withdrawn / abandoned |
| Eiffel Solar POI 2 Solar ยท Paris Farm Solar, LLC |
200 MW | Withdrawn / abandoned |
| Miranda ESS Battery storage |
200 MW | Withdrawn / abandoned |
| GYPSY ESS Battery storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project AE2-260, Greensville County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project J1469, Crittenden County Solar |
200 MW | Withdrawn / abandoned |
| Solar project 390, Tallahatchie County Solar |
200 MW | Withdrawn / abandoned |
| Mockingbird Solar Solar ยท Lincoln Clean Energy Development |
200 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2019-024, Woodford County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1322, Eaton County Solar |
200 MW | Withdrawn / abandoned |
| Solar project 360, Simpson County Solar |
200 MW | Withdrawn / abandoned |
| Solar project 359, Logan County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1428, Cass County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project Q73, Los Angeles County Battery storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project AE2-153, Kankakee County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J1384, Evangeline Parish County Solar |
200 MW | Withdrawn / abandoned |
| Cardinal Storage Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project AF1-298, Delaware County Solar |
200 MW | Withdrawn / abandoned |
| Primavera Storage Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project IC-819, Douglas County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project LGE-GIS-2019-027, Scott County Solar |
200 MW | Withdrawn / abandoned |
| Solar + storage project TCS-50, Clark County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project J1395, Lyon County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J1452, Red River Parish County Solar |
200 MW | Withdrawn / abandoned |
| Solar + storage project IA-PNM-2019-17, Bernalillo County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project J1204, Cumberland County Solar |
199 MW | Withdrawn / abandoned |
| Solar + storage project AE2-266, St. Joseph County Solar + storage |
199 MW | Withdrawn / abandoned |
| Onshore wind project AE2-174, Seneca County Onshore wind |
198 MW | Withdrawn / abandoned |
| Solar + storage project IA-PNM-2019-20, San Juan County Solar + storage |
198 MW | Withdrawn / abandoned |
| Solar + storage project IA-PNM-2019-16, Torrance County Solar + storage |
198 MW | Withdrawn / abandoned |
| Battery storage project AF1-306, Elk County Battery storage ยท Seven Creek Energy, LLC |
197 MW | Withdrawn / abandoned |
| Solar project GI-84, New Madrid County Solar |
196 MW | Withdrawn / abandoned |
| Poppy Solar |
185 MW | Withdrawn / abandoned |
| Solar project AE2-146, Potter County Solar |
183 MW | Withdrawn / abandoned |
| Solar project GEN-2019-033, Knox County Solar |
182 MW | Withdrawn / abandoned |
| Corcair Hybrid Solar Solar + storage |
181 MW | Withdrawn / abandoned |
| Niagara Dolomite Solar Solar ยท Niagara Dolomite Solar, LLC |
180 MW | Withdrawn / abandoned |
| Solar project AF1-221, Franklin County Solar ยท Yellow Perch Solar LLC |
180 MW | Withdrawn / abandoned |
| Solar project AF1-113, Auglaize County Solar |
180 MW | Withdrawn / abandoned |
| Battery Storage Battery storage |
180 MW | Withdrawn / abandoned |
| Eldean Solar Solar |
178 MW | Withdrawn / abandoned |
| Brushy Creek Solar SLF Solar ยท Brushy Creek Solar LLC |
177 MW | Withdrawn / abandoned |
| Solar project AF1-012, Lee County Solar |
175 MW | Withdrawn / abandoned |
| Gas project 370, Yellowstone County Gas |
175 MW | Withdrawn / abandoned |
| Solar project 368, Chickasaw County Solar |
175 MW | Withdrawn / abandoned |
| Solar project J1237, Washtenaw County Solar |
175 MW | Withdrawn / abandoned |
| Solar project 361, Warren County Solar |
175 MW | Withdrawn / abandoned |
| Onshore wind project AE2-295, Schuylkill County Onshore wind |
175 MW | Withdrawn / abandoned |
| Solar project 363, Logan County Solar |
173 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)247 ยท 41.2 GW
- CAISO (California)95 ยท 39.6 GW
- PJM (Mid-Atlantic, Midwest)409 ยท 38.5 GW
- Southeast (non-ISO utilities)199 ยท 37.4 GW
- MISO (Midcontinent)153 ยท 21.3 GW
- ERCOT (Texas)109 ยท 20.7 GW
- NYISO (New York)135 ยท 14.9 GW
- SPP (Southwest Power Pool)57 ยท 6,718 MW
- ISO-NE (New England)69 ยท 6,220 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)