SOLAR Β· ERCOT

Mockingbird Solar

Mockingbird Solar is a 200 MW solar request withdrawn in the ERCOT interconnection queue, in Hill County, Texas.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2019 (completed)
  2. Withdrawn / abandonedMar 2020 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
21INR0419
Grid region
ERCOT (Texas)
Developer
Lincoln Clean Energy Development
Connection point (POI)
tap 138kV 3522 Hillsboro - 3546 Whitney
Location
Hill County, Texas
Technology
Solar: 200 MW
Total requested
200 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
25 August 2019
Proposed online date
December 2021
Withdrawn
March 2020

Location

Marker shows the centre of Hill County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Hill County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem