🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 73

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 73 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 37, Utah County
Gas
310 MWWithdrawn / abandoned Utah, UTWest Jan 2004target 2006
Twilight
Solar + storage
310 MWWithdrawn / abandoned CACAISO Apr 2023target 2026
Solar project GI-2023-4, Adams County
Solar
310 MWWithdrawn / abandoned Adams, COWest May 2023target 2027
Homestead Energy Center
Battery storage
310 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Onshore wind project GEN-2016-114, Mcpherson County
Onshore wind
310 MWWithdrawn / abandoned Mcpherson, KSSPP Oct 20202020
Battery storage project Q535, Maricopa County
Battery storage
310 MWWithdrawn / abandoned Maricopa, AZWest Aug 2023target 2028
Fletcher BESS
Battery storage · Archer Energy Center, LLC
310 MWWithdrawn / abandoned ERCOT Jul 2024target 2027
Redpoint
Solar + storage
310 MWWithdrawn / abandoned Kings, CACAISO Apr 2023target 2028
Anacapa
Solar + storage
309 MWWithdrawn / abandoned Santa Barbara, CACAISO Apr 2020target 2023
Sand Solar
Solar
309 MWWithdrawn / abandoned San Bernardino, CACAISO May 2016target 2021
Key Storage 2
Battery storage
309 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2024
Other project AD2-080, St. Joseph County
Other
309 MWWithdrawn / abandoned St. Joseph, INPJM Mar 2018target 2020
Diablo Energy Facility
Gas
309 MWWithdrawn / abandoned Contra Costa, CACAISO Apr 2014target 2017
Gas project X2-067, Kent County
Gas
309 MWWithdrawn / abandoned Kent, DEPJM Jul 2011target 2016
Gas project 8, Pierce County
Gas
309 MWWithdrawn / abandoned Pierce, WAWest Jan 2006target 2009
Solar + storage project J1756, Shelby County
Solar + storage
309 MWWithdrawn / abandoned Shelby, INMISO Jun 2020target 2023
Marnier
Solar + storage
309 MWWithdrawn / abandoned Merced, CACAISO Apr 2021target 2024
HillRich
Battery storage
309 MWWithdrawn / abandoned Santa Clara, CACAISO Apr 2023target 2028
Barrenspring
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Vestal Valley
Solar + storage
308 MWWithdrawn / abandoned Tulare, CACAISO Apr 2019target 2023
Japatul Valley Storage
Battery storage
308 MWWithdrawn / abandoned San Diego, CACAISO Apr 2021target 2024
San Bernardino BESS
Battery storage
308 MWWithdrawn / abandoned San Bernardino, CACAISO Apr 2019target 2022
Syrah Storage Center
Battery storage
308 MWWithdrawn / abandoned CACAISO Apr 2023target 2030
Robin 2
Solar + storage
308 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2020target 2023
Hinson BESS
Battery storage
308 MWWithdrawn / abandoned Los Angeles, CACAISO Apr 2019target 2022
Gas project AA1-045, Venango County
Gas
308 MWWithdrawn / abandoned Venango, PAPJM Aug 2014target 2015
Onshore wind project Company 244, Nye County
Onshore wind
308 MWWithdrawn / abandoned Nye, NVWest Mar 2023target 2027
Onshore wind project C1-49, Bonneville County
Onshore wind
308 MWWithdrawn / abandoned Bonneville, IDWest May 2021target 2024
Genoa Energy Storage 2
Battery storage
308 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Barbers Hill BESS
Battery storage · Black Mountain Energy Storage II
308 MWWithdrawn / abandoned ERCOT Jan 2023target 2027
Baylands Power Bank
Battery storage
308 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Easter Wind
Onshore wind · TriGlobal
308 MWWithdrawn / abandoned Castro, TXERCOT Dec 2013target 2021
Casy Solar
Solar + storage
308 MWWithdrawn / abandoned Fresno, CACAISO Apr 2018target 2022
Hog Island
Solar + storage
307 MWWithdrawn / abandoned Tulare, CACAISO Apr 2021target 2024
Gas project GI-RSC-2025-01, Moffat County
Gas
307 MWWithdrawn / abandoned Moffat, COWest Jul 2025target 2029
Onshore wind project G0595, Lewis County
Onshore wind
307 MWWithdrawn / abandoned Lewis, WAWest Jul 2018target 2022
Valhalla Solar
Solar · Industrial Papa Project LLC
307 MWWithdrawn / abandoned Brazoria, TXERCOT Mar 2023target 2026
Vantage
Battery storage
307 MWWithdrawn / abandoned San Diego, CACAISO Apr 2023target 2030
Gas project 2022-G1
Gas
307 MWWithdrawn / abandoned West Feb 2022target 2026
Box Canyon Energy Storage
Other · Box Canyon Energy Storage Project, LLC
306 MWWithdrawn / abandoned Callahan, TXERCOT Jan 2024target 2027
Mountain Valley Storage
Battery storage
306 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Warm Water
Battery storage
306 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Plymouth Energy
Gas · Plymouth Energy, LLC
306 MWWithdrawn / abandoned Benton, WAWest Jan 2002target 2004
Gas project GEN-2009-002, Lubbock County
Gas
306 MWWithdrawn / abandoned Lubbock, TXSPP Jan 2009target 2012
Barbosa
Battery storage
306 MWWithdrawn / abandoned CACAISO Apr 2023target 2027
Onshore wind project IA-PNM-2025-16, Torrance County
Onshore wind
306 MWWithdrawn / abandoned Torrance, NMWest Mar 2025target 2029
Gas project 262, Payette County
Gas
306 MWWithdrawn / abandoned Payette, IDWest Jun 2008target 2012
Grape Valley Storage
Battery storage
306 MWWithdrawn / abandoned CACAISO Apr 2023target 2029
Copernicus
Solar + storage
306 MWWithdrawn / abandoned CACAISO Apr 2021target 2024
Goose Foot Energy Storage
Battery storage · Goose Foot Energy Storage Project, LLC
306 MWWithdrawn / abandoned ERCOT Dec 2024target 2028
Page 73 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)