Redpoint

Redpoint is a 310 MW solar + storage request withdrawn in the CAISO interconnection queue, in Kings County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2307
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
HENRIETTA 230 kV
Location
Kings County, California
Technology
Solar: 155 MW Β· Battery: 154 MW
Total requested
310 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
April 2028
Withdrawn
December 2025

Location

Marker shows the centre of Kings County; the queue data does not give exact sites.