BATTERY STORAGE Β· CAISO

Homestead Energy Center

Homestead Energy Center is a 310 MW battery storage request withdrawn in the CAISO interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
caiso_c15_183
Grid region
CAISO (California)
Connection point (POI)
Lone Tree 230kV
Location
California
Technology
Battery: 310 MW
Total requested
310 MW
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
September 2029
Withdrawn
December 2024

Location

No county location in the queue data.

Power plants in California Β· Transmission lines in California

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem