United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2024 requests) โ page 7
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Ridley Solar SLF Solar ยท Ridley Solar Project, LLC |
201 MW | Withdrawn / abandoned |
| Battery storage project 24-247, Columbia County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3321, Wayne County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project 24-254, Washington County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project 24-250, Clackamas County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar + storage project J3309, Copiah County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project J3572, Catahoula Parish County Solar |
200 MW | Withdrawn / abandoned |
| Blue Frost Solar Solar ยท Blue Frost Energy Center, LLC |
200 MW | Withdrawn / abandoned |
| Solar project J3241, Lincoln County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2024-059, Stanley County Onshore wind |
200 MW | Withdrawn / abandoned |
| Other project IC-1243, Pearl River County Other |
200 MW | Withdrawn / abandoned |
| Solar project J3375, Washington County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project J3247, Vigo County Battery storage |
200 MW | Withdrawn / abandoned |
| Blue Frost Storage II Battery storage ยท Blue Frost Energy Center, LLC |
200 MW | Withdrawn / abandoned |
| NY125B - Two Rivers Solar Solar ยท Boralex US Development LLC |
200 MW | Withdrawn / abandoned |
| Battery storage project J3258, Ottawa County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3323, Knox County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J3503, Newton County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J3573, Morehouse Parish County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J3475, Mason County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J3627, Craighead County Solar |
200 MW | Withdrawn / abandoned |
| Solar + storage project 2024-G1, Tehama County Solar + storage |
200 MW | Withdrawn / abandoned |
| Rosalen Solar Energy Center Solar + storage ยท EDF Renewables Development, Inc. |
200 MW | Withdrawn / abandoned |
| Battery storage project 665, Shelby County Battery storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project J3667, Dickey County Onshore wind |
200 MW | Withdrawn / abandoned |
| Battery storage project J3320, Ottawa County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3450, Panola County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project J3726, Hancock County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project 24-249, Washington County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3300, Craighead County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J3721, Spencer County Solar |
200 MW | Withdrawn / abandoned |
| Sweet Valley Storage Battery storage ยท Sweet Valley Energy Center, LLC |
200 MW | Withdrawn / abandoned |
| Solar project J3350, Randolph County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project 24-256, Washington County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3261, Tunica County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project 621, Bay County Battery storage ยท FPL |
200 MW | Withdrawn / abandoned |
| Solar project J3739, Warren County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project J3526, Goodhue County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3783, Cross County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project J3851, Mcdonough County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project J3567, Calhoun County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project 617, Columbia County Battery storage ยท FPL |
200 MW | Withdrawn / abandoned |
| Solar project J3484, Union County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project J3490, Caldwell County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project 24-257, Marion County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J3276, Pulaski County Solar |
200 MW | Withdrawn / abandoned |
| Solar + storage project J3649, Houghton County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project J3867, Iroquois County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project IC-1269, Putnam County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project 614, Calhoun County Battery storage ยท FPL |
200 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- MISO (Midcontinent)411 ยท 78.5 GW
- NYISO (New York)294 ยท 63.3 GW
- West (non-ISO utilities)237 ยท 46.1 GW
- Southeast (non-ISO utilities)195 ยท 32.8 GW
- ISO-NE (New England)97 ยท 13.2 GW
- ERCOT (Texas)50 ยท 10.0 GW
- SPP (Southwest Power Pool)29 ยท 7,503 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)