๐Ÿ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more โ†’ Skip to main content

United States โ€บ Grid โ€บ Interconnection queues

OCTARY USA ยท INTERCONNECTION QUEUES

Withdrawn queue requests in the USA (2024 requests) โ€” page 7

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,313251.4 GW
Active in queue285.2 GW1,283 requests
Agreement signed30.3 GW117 requests
Withdrawn1,313251.4 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,313 requests ยท page 7 of 27
ProjectCapacityStatusLocationRegionQueuedOnline
Ridley Solar SLF
Solar ยท Ridley Solar Project, LLC
201 MWWithdrawn / abandoned ERCOT Jul 2024target 2029
Battery storage project 24-247, Columbia County
Battery storage
200 MWWithdrawn / abandoned Columbia, ORWest May 2024target 2027
Solar project J3321, Wayne County
Solar
200 MWWithdrawn / abandoned Wayne, ILMISO Apr 2024target 2028
Battery storage project 24-254, Washington County
Battery storage
200 MWWithdrawn / abandoned Washington, ORWest May 2024target 2027
Battery storage project 24-250, Clackamas County
Battery storage
200 MWWithdrawn / abandoned Clackamas, ORWest May 2024target 2027
Solar + storage project J3309, Copiah County
Solar + storage
200 MWWithdrawn / abandoned Copiah, MSMISO Apr 2024target 2028
Solar project J3572, Catahoula Parish County
Solar
200 MWWithdrawn / abandoned Catahoula Parish, LAMISO Apr 2024target 2028
Blue Frost Solar
Solar ยท Blue Frost Energy Center, LLC
200 MWWithdrawn / abandoned Montgomery, NYNYISO Sep 2024
Solar project J3241, Lincoln County
Solar
200 MWWithdrawn / abandoned Lincoln, MSMISO Apr 2024target 2028
Onshore wind project GEN-2024-059, Stanley County
Onshore wind
200 MWWithdrawn / abandoned Stanley, SDSPP Oct 2024target 2028
Other project IC-1243, Pearl River County
Other
200 MWWithdrawn / abandoned Pearl River, MSSoutheast Mar 2024
Solar project J3375, Washington County
Solar
200 MWWithdrawn / abandoned Washington, MSMISO Apr 2024target 2028
Battery storage project J3247, Vigo County
Battery storage
200 MWWithdrawn / abandoned Vigo, INMISO Apr 2024target 2028
Blue Frost Storage II
Battery storage ยท Blue Frost Energy Center, LLC
200 MWWithdrawn / abandoned Montgomery, NYNYISO Sep 2024
NY125B - Two Rivers Solar
Solar ยท Boralex US Development LLC
200 MWWithdrawn / abandoned St. Lawrence, NYNYISO Aug 2024
Battery storage project J3258, Ottawa County
Battery storage
200 MWWithdrawn / abandoned Ottawa, MIMISO Apr 2024target 2028
Solar project J3323, Knox County
Solar
200 MWWithdrawn / abandoned Knox, ILMISO Apr 2024target 2028
Solar project J3503, Newton County
Solar
200 MWWithdrawn / abandoned Newton, INMISO Apr 2024target 2028
Solar project J3573, Morehouse Parish County
Solar
200 MWWithdrawn / abandoned Morehouse Parish, LAMISO Apr 2024target 2028
Solar project J3475, Mason County
Solar
200 MWWithdrawn / abandoned Mason, ILMISO Apr 2024target 2028
Solar project J3627, Craighead County
Solar
200 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2027
Solar + storage project 2024-G1, Tehama County
Solar + storage
200 MWWithdrawn / abandoned Tehama, CAWest Sep 2024target 2028
Rosalen Solar Energy Center
Solar + storage ยท EDF Renewables Development, Inc.
200 MWWithdrawn / abandoned Wayne, NYNYISO Aug 2024
Battery storage project 665, Shelby County
Battery storage
200 MWWithdrawn / abandoned Shelby, TNSoutheast Oct 2024
Onshore wind project J3667, Dickey County
Onshore wind
200 MWWithdrawn / abandoned Dickey, NDMISO Apr 2024target 2028
Battery storage project J3320, Ottawa County
Battery storage
200 MWWithdrawn / abandoned Ottawa, MIMISO Apr 2024target 2028
Solar project J3450, Panola County
Solar
200 MWWithdrawn / abandoned Panola, MSMISO Apr 2024target 2028
Battery storage project J3726, Hancock County
Battery storage
200 MWWithdrawn / abandoned Hancock, KYMISO Mar 2024target 2027
Battery storage project 24-249, Washington County
Battery storage
200 MWWithdrawn / abandoned Washington, ORWest May 2024target 2027
Solar project J3300, Craighead County
Solar
200 MWWithdrawn / abandoned Craighead, ARMISO Apr 2024target 2027
Solar project J3721, Spencer County
Solar
200 MWWithdrawn / abandoned Spencer, INMISO Mar 2024target 2028
Sweet Valley Storage
Battery storage ยท Sweet Valley Energy Center, LLC
200 MWWithdrawn / abandoned Genesee, NYNYISO Sep 2024
Solar project J3350, Randolph County
Solar
200 MWWithdrawn / abandoned Randolph, MOMISO Apr 2024target 2028
Battery storage project 24-256, Washington County
Battery storage
200 MWWithdrawn / abandoned Washington, ORWest May 2024target 2027
Solar project J3261, Tunica County
Solar
200 MWWithdrawn / abandoned Tunica, MSMISO Mar 2024target 2028
Battery storage project 621, Bay County
Battery storage ยท FPL
200 MWWithdrawn / abandoned Bay, FLSoutheast Jan 2024target 2027
Solar project J3739, Warren County
Solar
200 MWWithdrawn / abandoned Warren, ILMISO Apr 2024target 2028
Battery storage project J3526, Goodhue County
Battery storage
200 MWWithdrawn / abandoned Goodhue, MNMISO Apr 2024target 2030
Solar project J3783, Cross County
Solar
200 MWWithdrawn / abandoned Cross, ARMISO Apr 2024target 2028
Battery storage project J3851, Mcdonough County
Battery storage
200 MWWithdrawn / abandoned Mcdonough, ILMISO Dec 2024target 2030
Battery storage project J3567, Calhoun County
Battery storage
200 MWWithdrawn / abandoned Calhoun, ARMISO Apr 2024target 2026
Battery storage project 617, Columbia County
Battery storage ยท FPL
200 MWWithdrawn / abandoned Columbia, FLSoutheast Jan 2024target 2028
Solar project J3484, Union County
Solar
200 MWWithdrawn / abandoned Union, ARMISO Apr 2024target 2027
Battery storage project J3490, Caldwell County
Battery storage
200 MWWithdrawn / abandoned Caldwell, KYMISO Mar 2024target 2027
Battery storage project 24-257, Marion County
Battery storage
200 MWWithdrawn / abandoned Marion, ORWest May 2024target 2027
Solar project J3276, Pulaski County
Solar
200 MWWithdrawn / abandoned Pulaski, ILMISO Apr 2024target 2028
Solar + storage project J3649, Houghton County
Solar + storage
200 MWWithdrawn / abandoned Houghton, MIMISO Apr 2024target 2028
Solar project J3867, Iroquois County
Solar
200 MWWithdrawn / abandoned Iroquois, ILMISO Dec 2024target 2029
Battery storage project IC-1269, Putnam County
Battery storage
200 MWWithdrawn / abandoned Putnam, GASoutheast Mar 2024
Battery storage project 614, Calhoun County
Battery storage ยท FPL
200 MWWithdrawn / abandoned Calhoun, FLSoutheast Jan 2024target 2029

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)