BATTERY STORAGE Β· MISO

Battery storage project J3726, Hancock County

Battery storage project J3726, Hancock County is a 200 MW battery storage request withdrawn in the MISO interconnection queue, in Hancock County, Kentucky, connecting to BIG RIVERS ELECTRIC CORPORATION.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2024 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3726
Grid region
MISO (Midcontinent)
Utility / transmission owner
BIG RIVERS ELECTRIC CORPORATION
Connection point (POI)
Skillman
Location
Hancock County, Kentucky
Technology
Battery: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
18 March 2024
Proposed online date
January 2027
Withdrawn
December 2025

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.