Hydro project G032, Hancock County

Hydro project G032, Hancock County is a 95.0 MW hydro request built and operating in the MISO interconnection queue, in Hancock County, Kentucky.

Queue statusOperating
  1. PlanningQueued Mar 2000 (completed)
  2. ConsentedNov 2003 (completed)
  3. Construction (completed)
  4. OperatingJun 2001 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G032
Grid region
MISO (Midcontinent)
Connection point (POI)
Cloverport 138 kV Substation
Location
Hancock County, Kentucky
Technology
Hydro: 95.0 MW
Total requested
95.0 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
1 March 2000
Agreement signed
14 November 2003
Proposed online date
June 2001
Came online
June 2001

Location

Marker shows the centre of Hancock County; the queue data does not give exact sites.

Power plants in Kentucky · Transmission lines in Kentucky

Other requests in Hancock County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem