πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR + STORAGE Β· WEST

Solar + storage project 2024-G1, Tehama County

Solar + storage project 2024-G1, Tehama County is a 200 MW solar + storage request withdrawn in the West interconnection queue, in Tehama County, California, connecting to WAPA Sierra Nevada.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2024 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2024-G1
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA Sierra Nevada
Connection point (POI)
Olinda-O'Banion #1 230 kV Transmission Line
Location
Tehama County, California
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
Energy only (ERIS)
Study phase
Not Started
Queue status
Withdrawn
Entered queue
3 September 2024
Proposed online date
December 2028

Location

Marker shows the centre of Tehama County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Tehama County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem