πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR + STORAGE Β· CAISO

Mandorla

Mandorla is a 206 MW solar + storage request withdrawn in the CAISO interconnection queue, in Tehama County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2023 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
2330
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
GLENN 230 kV
Location
Tehama County, California
Technology
Solar: 103 MW Β· Battery: 103 MW
Total requested
206 MW
Service type
Energy only (ERIS)
Study phase
Caiso Cluster 15 Unvalidated
Queue status
Withdrawn
Entered queue
17 April 2023
Proposed online date
June 2030
Withdrawn
December 2025

Location

Marker shows the centre of Tehama County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Tehama County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem