BATTERY STORAGE Β· SOUTHEAST

Battery storage project IC-1269, Putnam County

Battery storage project IC-1269, Putnam County is a 200 MW battery storage request withdrawn in the Southeast interconnection queue, in Putnam County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2024 (completed)
  2. Withdrawn / abandonedJun 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-1269
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Eatonton Primary Substation 230 kV Bus
Location
Putnam County, Georgia
Technology
Battery: 200 MW
Total requested
200 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
25 March 2024
Withdrawn
June 2024

Location

Marker shows the centre of Putnam County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Putnam County