SOLAR + STORAGE Β· MISO

Solar + storage project J3309, Copiah County

Solar + storage project J3309, Copiah County is a 200 MW solar + storage request withdrawn in the MISO interconnection queue, in Copiah County, Mississippi, connecting to ENTERGY MISSISSIPPI, LLC..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2024 (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J3309
Grid region
MISO (Midcontinent)
Utility / transmission owner
ENTERGY MISSISSIPPI, LLC.
Connection point (POI)
FRANKLIN EHV - RAY BRASWELL EHV 500.0kV
Location
Copiah County, Mississippi
Technology
Solar: 200 MW Β· Battery
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 1
Queue status
Withdrawn
Entered queue
15 April 2024
Proposed online date
June 2028
Withdrawn
May 2025

Location

Marker shows the centre of Copiah County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem