Solar interconnection queue in the USA — page 52

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown2,995427.5 GW
Active in queue427.5 GW2,995 requests
Agreement signed108.2 GW781 requests
Withdrawn9,252860.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

2,995 requests · page 52 of 60
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project GI-2010-4, Alamosa County
Solar
30.0 MWAgreement signed Alamosa, COWest Feb 2010target 2012
Spinel Solar
Solar
30.0 MWPaused / redesign Medina, TXERCOT Aug 2017
Solar project 957086, Darlington County
Solar
30.0 MWIn study Darlington, SCSoutheast Jun 2024
Solar project 337, Lake County
Solar
30.0 MWAgreement signed Lake, TNSoutheast Jan 2018target 2020
Solar project AH2-117, Pike County
Solar
30.0 MWIn study Pike, KYPJM Feb 2022target 2026
Solar project AG2-081, Montgomery County
Solar · SR Fayette II, LLC
30.0 MWIn study Montgomery, KYPJM Mar 2025target 2024
Solar project J2908, Morgan County
Solar
30.0 MWIn study Morgan, ILMISO Jul 20222023
Solar project AH2-057, Buckingham County
Solar
29.9 MWIn study Buckingham, VAPJM Dec 2021target 2025
Solar project 287, Fairfield County
Solar
29.7 MWIn study Fairfield, SCSoutheast May 2025target 2027
Solar project AI2-471, Montour County
Solar
29.5 MWIn study Montour, PAPJM Mar 2023target 2025
Solar project AI2-338, Charles City County
Solar
29.2 MWIn study Charles City, VAPJM Mar 2023target 2024
Solar project AI2-473, Montour County
Solar
29.0 MWIn study Montour, PAPJM Mar 2023target 2026
Solar project AI1-119, Kendall County
Solar
28.8 MWIn study Kendall, ILPJM Sep 2022target 2026
Solar project AI2-152, Madison County
Solar
28.8 MWIn study Madison, INPJM Mar 2023target 2025
Solar project AI2-410, Dekalb County
Solar
28.5 MWIn study Dekalb, ILPJM Mar 2023target 2026
Solar project 572354, Cherokee County
Solar
28.3 MWAgreement signed Cherokee, SCSoutheast Jun 2022target 2027
Solar project AH2-379, Worcester County
Solar
28.3 MWIn study Worcester, MDPJM Mar 2022target 2026
Solar project AI2-424, Huntington County
Solar
28.0 MWIn study Huntington, INPJM Mar 2023target 2028
Solar project AI2-339, Nicholas County
Solar
26.8 MWIn study Nicholas, WVPJM Mar 2023target 2024
Solar project AI2-427, Licking County
Solar
26.4 MWIn study Licking, OHPJM Mar 2023target 2027
Solar project 957449, Greenwood County
Solar
26.1 MWIn study Greenwood, SCSoutheast Jun 2024
360 Solar Center, LLC
Solar · 360 Solar Center, LLC
26.0 MWIn study Chesterfield, VAPJM Feb 2025target 2023
360 Solar Center, LLC
Solar · 360 Solar Center, LLC
26.0 MWIn study Chesterfield, VAPJM Feb 2025target 2023
Blue Creek Wind Farm
Solar
26.0 MWPaused / redesign Van Wert, OHPJM Sep 2018target 2024
Solar project AH2-263, Marion County
Solar
25.8 MWIn study Marion, KYPJM Mar 2022target 2026
Solar project AH1-570
Solar · South Fork Solar, LLC
25.0 MWIn study KYPJM Mar 2025target 2024
Solar project 957084, Darlington County
Solar
25.0 MWIn study Darlington, SCSoutheast Jun 2024
Solar project AH2-266, Charles County
Solar
25.0 MWIn study Charles, MDPJM Mar 2022target 2026
Solar project T2-079, Jefferson County
Solar
25.0 MWIn study Jefferson, ORWest Sep 2025target 2026
Fluorite Solar
Solar
25.0 MWPaused / redesign Uvalde, TXERCOT Aug 2017
Amelia Energy Facility
Solar · Amelia Energy Facility, LLC
25.0 MWIn study Amelia, VAPJM Feb 2020target 2022
Poseidon Solar 2
Solar · Poseidon Energy, LLC
25.0 MWIn study Fayette, PAPJM Feb 2025target 2024
Solar
Solar
25.0 MWIn study Hartford, CTISO-NE Apr 2022target 2027
Oswego Clean Energy
Solar · Oswego Clean Energy Holdings
24.9 MWIn study Oswego, NYNYISO Sep 2024target 2026
Hayhurst Texas Solar
Solar · Hayhurst Texas Solar, LLC
24.8 MWAgreement signed Culberson, TXERCOT Aug 2020target 2025
Dynamo Solar
Solar
24.5 MWAgreement signed Napa, CACAISO Apr 2019target 2027
Solar project AI2-013, Grundy County
Solar
24.1 MWIn study Grundy, ILPJM Nov 2022target 2026
Solar project AI2-154, Centre County
Solar
24.0 MWIn study Centre, PAPJM Mar 2023target 2025
Solar project AI2-135, Mclean County
Solar
24.0 MWIn study Mclean, ILPJM Feb 2023target 2025
Solar project AI2-169, Cass County
Solar
24.0 MWIn study Cass, MIPJM Mar 2023target 2025
Solar project AI2-418, Allen County
Solar
24.0 MWIn study Allen, INPJM Mar 2023target 2026
Solar project J1927, Muscatine County
Solar
23.4 MWIn study Muscatine, IAMISO Dec 2021target 2027
Solar project AI2-340, Van Buren County
Solar
23.1 MWIn study Van Buren, MIPJM Mar 2023target 2025
Solar project AI2-341, Marion County
Solar
22.8 MWIn study Marion, OHPJM Mar 2023target 2024
Solar project J1814, Dickinson County
Solar
22.5 MWAgreement signed Dickinson, MIMISO Jun 2020target 2026
Solar project LGE-GIS-2024-004, Mercer County
Solar
22.0 MWIn study Mercer, KYSoutheast Apr 2024target 2026
Solar project J3993, Wayne County
Solar
21.4 MWIn study Wayne, ILMISO Apr 2025target 2027
Solar project AH1-059, Knox County
Solar · Frasier Solar, LLC
21.0 MWIn study Knox, OHPJM Mar 2025target 2024
Solar project AI2-374, Bath County
Solar
20.6 MWIn study Bath, KYPJM Mar 2023target 2025
Solar project AI2-415, Butler County
Solar
20.3 MWIn study Butler, PAPJM Mar 2023target 2026
Page 52 of 60

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)