United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1814, Dickinson County

Solar project J1814, Dickinson County is a 22.5 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Dickinson County, Michigan, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusConsented
  1. PlanningQueued Jun 2020 (completed)
  2. ConsentedFeb 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
J1814
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Nordic
Location
Dickinson County, Michigan
Technology
Solar: 22.5 MW
Total requested
22.5 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Not Started
Queue status
Active
Entered queue
24 June 2020
Agreement signed
26 February 2024
Proposed online date
September 2026

Location

Marker shows the centre of Dickinson County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Dickinson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem