United States › Grid › Interconnection queues › Michigan
SOLAR · MISOSolar project J1814, Dickinson County
Solar project J1814, Dickinson County is a 22.5 MW solar request with a signed interconnection agreement in the MISO interconnection queue, in Dickinson County, Michigan, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusConsented
- PlanningQueued Jun 2020 (completed)
- ConsentedFeb 2024 (current stage)
- Construction (not yet reached)
- OperatingTarget Sep 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- J1814
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Nordic
- Location
- Dickinson County, Michigan
- Technology
- Solar: 22.5 MW
- Total requested
- 22.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Not Started
- Queue status
- Active
- Entered queue
- 24 June 2020
- Agreement signed
- 26 February 2024
- Proposed online date
- September 2026
Location
Marker shows the centre of Dickinson County; the queue data does not give exact sites.
Other requests in Dickinson County
- Solar project J2316, Dickinson CountySolar · 77.5 MW · in study
- Solar project J4085, Dickinson CountySolar · 42.0 MW · in study
- Solar project J4169, Dickinson CountySolar · 6.0 MW · in study
- Other project G344, Dickinson CountyOther · 15.0 MW · built
- Gas project J353, Dickinson CountyGas · 725 MW · withdrawn
- Gas project J352, Dickinson CountyGas · 362 MW · withdrawn
- Solar project J3641, Dickinson CountySolar · 100 MW · withdrawn
- Solar project J3642, Dickinson CountySolar · 60.0 MW · withdrawn
- Battery storage project J3638, Dickinson CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem