OTHER · MISOOther project G344, Dickinson County
Other project G344, Dickinson County is a 15.0 MW other request built and operating in the MISO interconnection queue, in Dickinson County, Michigan.
Request details
- Queue ID
- G344
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Plains Substation
- Location
- Dickinson County, Michigan
- Technology
- Diesel: 15.0 MW
- Total requested
- 15.0 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 1 June 2003
- Agreement signed
- 16 September 2003
Location
Marker shows the centre of Dickinson County; the queue data does not give exact sites.
Other requests in Dickinson County
- Solar project J1814, Dickinson CountySolar · 22.5 MW · agreement signed
- Solar project J2316, Dickinson CountySolar · 77.5 MW · in study
- Solar project J4085, Dickinson CountySolar · 42.0 MW · in study
- Solar project J4169, Dickinson CountySolar · 6.0 MW · in study
- Gas project J353, Dickinson CountyGas · 725 MW · withdrawn
- Gas project J352, Dickinson CountyGas · 362 MW · withdrawn
- Solar project J3641, Dickinson CountySolar · 100 MW · withdrawn
- Solar project J3642, Dickinson CountySolar · 60.0 MW · withdrawn
- Battery storage project J3638, Dickinson CountyBattery storage · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem