United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in PJM (Mid-Atlantic, Midwest) — page 50

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5,226638.1 GW
Active in queue140.4 GW1,248 requests
Agreement signed35.0 GW343 requests
Withdrawn5,226638.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

5,226 requests · page 50 of 105
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AC2-039, Athens County
Solar
43.0 MWWithdrawn / abandoned Athens, OHPJM Feb 2017target 2019
Mountain Top
Onshore wind
42.9 MWWithdrawn / abandoned Luzerne, PAPJM Oct 2003target 2005
Battery storage project AF2-023, Salem County
Battery storage
42.5 MWWithdrawn / abandoned Salem, NJPJM Nov 2019target 2021
Battery storage project AF2-329, Kendall County
Battery storage · Plano Skies Energy Center, LLC
42.2 MWWithdrawn / abandoned Kendall, ILPJM Mar 2020target 2023
Solar project AH1-569, Union County
Solar · Glacier Ridge Solar, LLC
42.0 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2024
Solar + storage project AI1-096
Solar + storage
42.0 MWWithdrawn / abandoned WVPJM Aug 2022target 2027
Solar project AE2-189, Butler County
Solar
42.0 MWWithdrawn / abandoned Butler, PAPJM Mar 2019target 2022
Battery storage project AH1-483, Union County
Battery storage
42.0 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2024
Solar project AF2-084, Union County
Solar
42.0 MWWithdrawn / abandoned Union, OHPJM Jan 2020target 2022
Solar + storage project AH1-536, Queen Anne's County
Solar + storage · Old Line Energy, LLC
41.8 MWWithdrawn / abandoned Queen Anne's, MDPJM Feb 2025target 2025
Gas project H23_W69, Summers County
Gas
41.0 MWWithdrawn / abandoned Summers, WVPJM Jan 2002target 2006
Solar project AG2-064, Caroline County
Solar
41.0 MWWithdrawn / abandoned Caroline, VAPJM Dec 2020target 2023
Hydro project I22, Summers County
Hydro
41.0 MWWithdrawn / abandoned Summers, WVPJM Jul 2002target 2004
Renovo Energy Center
Gas
41.0 MWWithdrawn / abandoned Clinton, PAPJM Sep 2015target 2019
Onshore wind project J01, Highland County
Onshore wind
41.0 MWWithdrawn / abandoned Highland, VAPJM Aug 2002target 2004
Solar project AG2-085, Delaware County
Solar · Royerton Solar, LLC
40.0 MWWithdrawn / abandoned Delaware, INPJM Mar 2025target 2023
University Park North Energy Center
Battery storage
40.0 MWWithdrawn / abandoned Will, ILPJM Sep 2020target 2027
Solar + storage project AI1-098, Pickaway County
Solar + storage
40.0 MWWithdrawn / abandoned Pickaway, OHPJM Aug 2022target 2026
Solar + storage project AG2-418, Perry County
Solar + storage · Wills Creek Solar LLC
40.0 MWWithdrawn / abandoned Perry, PAPJM Jan 2025target 2023
Gas project X1-047, New Castle County
Gas
40.0 MWWithdrawn / abandoned New Castle, DEPJM Mar 2011target 2011
Solar + storage project AG2-419, Caroline County
Solar + storage
40.0 MWWithdrawn / abandoned Caroline, MDPJM Mar 2021target 2023
Solar + storage project AG2-263, Fayette County
Solar + storage
40.0 MWWithdrawn / abandoned Fayette, OHPJM Mar 2021target 2023
Onshore wind project Q40, Clinton County
Onshore wind
40.0 MWWithdrawn / abandoned Clinton, PAPJM May 2006target 2009
Bellefontaine PV and BESS Project
Solar + storage · Hodson GreenDefine Blue Jacket LLC
40.0 MWWithdrawn / abandoned Logan, OHPJM Sep 2020target 2023
Solar project AH1-478, Columbia County
Solar
40.0 MWWithdrawn / abandoned Columbia, PAPJM Sep 2021target 2023
Solar project AD1-023, Bertie County
Solar
40.0 MWWithdrawn / abandoned Bertie, NCPJM Jun 2017target 2019
Solar project AH2-294, Grundy County
Solar
40.0 MWWithdrawn / abandoned Grundy, ILPJM Mar 2022target 2026
Solar project AH1-168, Caroline County
Solar
40.0 MWWithdrawn / abandoned Caroline, VAPJM Aug 2021target 2026
Battery storage project AH1-080, City Of Virginia Beach County
Battery storage
40.0 MWWithdrawn / abandoned City Of Virginia Beach, VAPJM Jul 2021target 2025
Solar project AF2-074, Gates County
Solar
40.0 MWWithdrawn / abandoned Gates, NCPJM Jan 2020target 2024
Battery storage project AH1-354, Stephenson County
Battery storage · Blue Violet Energy, LLC
40.0 MWWithdrawn / abandoned Stephenson, ILPJM Sep 2021target 2024
Solar project AE1-164, Accomack County
Solar
40.0 MWWithdrawn / abandoned Accomack, VAPJM Sep 2018target 2021
Solar project AB2-064, Van Wert County
Solar
40.0 MWWithdrawn / abandoned Van Wert, OHPJM Mar 2016target 2018
Onshore wind project T48, Mercer County
Onshore wind
40.0 MWWithdrawn / abandoned Mercer, OHPJM Sep 2007target 2013
Solar + storage project AF2-232, Columbia County
Solar + storage
40.0 MWWithdrawn / abandoned Columbia, PAPJM Mar 2020target 2021
Solar project AG2-663, Columbiana County
Solar
40.0 MWWithdrawn / abandoned Columbiana, OHPJM Mar 2021target 2025
Gas project Y2-110, Cape May County
Gas
40.0 MWWithdrawn / abandoned Cape May, NJPJM Nov 2012target 2016
Savage Mtn WF
Onshore wind
40.0 MWWithdrawn / abandoned Allegheny, PAPJM Mar 2002target 2011
Solar + storage project AG1-277, Luzerne County
Solar + storage · LU-Tank LLC
40.0 MWWithdrawn / abandoned Luzerne, PAPJM Sep 2020target 2022
Solar project AB2-103, Adams County
Solar
40.0 MWWithdrawn / abandoned Adams, OHPJM Apr 2016target 2017
Solar project AB2-147, Greensville County
Solar
40.0 MWWithdrawn / abandoned Greensville, VAPJM Apr 2016target 2017
Solar + storage project AG2-609, Orange County
Solar + storage
40.0 MWWithdrawn / abandoned Orange, VAPJM Mar 2021target 2023
Solar project AH1-202, Somerset County
Solar
40.0 MWWithdrawn / abandoned Somerset, PAPJM Sep 2021target 2023
Coal project AD2-078, Scioto County
Coal
40.0 MWWithdrawn / abandoned Scioto, OHPJM Mar 2018target 2020
Mountain Ridge Solar
Solar · Mango Solar LLC
40.0 MWWithdrawn / abandoned Somerset, PAPJM Feb 2025target 2023
Onshore wind project W4-019, Bureau County
Onshore wind
40.0 MWWithdrawn / abandoned Bureau, ILPJM Nov 2010target 2012
Solar project AG2-131, Van Buren County
Solar · CP South Branch LLC
40.0 MWWithdrawn / abandoned Van Buren, MIPJM Feb 2021target 2026
Solar project AH1-404, Highland County
Solar
40.0 MWWithdrawn / abandoned Highland, OHPJM Sep 2021target 2024
Carvers Creek LLC
Battery storage · Carvers Creek LLC
40.0 MWWithdrawn / abandoned Gloucester, VAPJM Sep 2021target 2024
Solar project AI2-033, Sussex County
Solar
40.0 MWWithdrawn / abandoned Sussex, VAPJM Jan 2023target 2024
Page 50 of 105

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)