United States › Grid › Interconnection queues › Pennsylvania

ONSHORE WIND · PJM

Savage Mtn WF

Savage Mtn WF is a 40.0 MW onshore wind request withdrawn in the PJM interconnection queue, in Allegheny County, Pennsylvania, connecting to APS.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2002 (completed)
  2. Withdrawn / abandonedNov 2009 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
I03_W74
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Savage 138kV
Location
Allegheny County, Pennsylvania
Technology
Wind: 40.0 MW
Total requested
40.0 MW
Service type
Energy only (ERIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Withdrawn
Entered queue
27 March 2002
Proposed online date
September 2011
Withdrawn
November 2009

Location

Marker shows the centre of Allegheny County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Allegheny County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem