United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
COAL Β· PJMLuke Paper
Luke Paper is a 8.0 MW coal request built and operating in the PJM interconnection queue, in Allegheny County, Pennsylvania, connecting to APS.
Request details
- Queue ID
- S38
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Westvaco 138kV
- Location
- Allegheny County, Pennsylvania
- Technology
- Coal: 8.0 MW
- Total requested
- 8.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Document Posted
- Queue status
- Operational
- Entered queue
- 7 May 2007
- Proposed online date
- January 2009
- Came online
- April 2009
Location
Marker shows the centre of Allegheny County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Allegheny County
- Battery storage project AH2-244, Allegheny CountyBattery storage Β· 25.0 MW Β· in study
- Battery storage project AH2-245, Allegheny CountyBattery storage Β· 25.0 MW Β· in study
- Solar project AG2-037, Allegheny CountySolar Β· 4.7 MW Β· in study
- Springdale CT3, CT4, ST5Gas Β· 525 MW Β· built
- Springdale 1 & 2Gas Β· 96.0 MW Β· built
- SpringdaleGas Β· 50.4 MW Β· built
- Pittsburgh International AirportGas Β· 14.4 MW Β· built
- AES Warrior Run Energy StorageBattery storage Β· 11.0 MW Β· built
- Coal project V1-013, Allegheny CountyCoal Β· 580 MW Β· withdrawn
- Allegheny Energy Center LLCGas Β· 541 MW Β· withdrawn
- Gas project G06_W47, Allegheny CountyGas Β· 500 MW Β· withdrawn
- Battery storage project AI1-176, Allegheny CountyBattery storage Β· 300 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem