United States βΊ Grid βΊ Interconnection queues βΊ Pennsylvania
BATTERY STORAGE Β· PJMBattery storage project AI1-176, Allegheny County
Battery storage project AI1-176, Allegheny County is a 300 MW battery storage request withdrawn in the PJM interconnection queue, in Allegheny County, Pennsylvania, connecting to DL.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2022 (completed)
- Withdrawn / abandonedMar 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AI1-176
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- DL
- Connection point (POI)
- Cheswick 138 kV
- Location
- Allegheny County, Pennsylvania
- Technology
- Battery: 300 MW
- Total requested
- 300 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 9 September 2022
- Proposed online date
- December 2025
- Withdrawn
- March 2024
Location
Marker shows the centre of Allegheny County; the queue data does not give exact sites.
Power plants in Pennsylvania Β· Transmission lines in Pennsylvania
Other requests in Allegheny County
- Battery storage project AH2-244, Allegheny CountyBattery storage Β· 25.0 MW Β· in study
- Battery storage project AH2-245, Allegheny CountyBattery storage Β· 25.0 MW Β· in study
- Solar project AG2-037, Allegheny CountySolar Β· 4.7 MW Β· in study
- Springdale CT3, CT4, ST5Gas Β· 525 MW Β· built
- Springdale 1 & 2Gas Β· 96.0 MW Β· built
- SpringdaleGas Β· 50.4 MW Β· built
- Pittsburgh International AirportGas Β· 14.4 MW Β· built
- AES Warrior Run Energy StorageBattery storage Β· 11.0 MW Β· built
- Luke PaperCoal Β· 8.0 MW Β· built
- Coal project V1-013, Allegheny CountyCoal Β· 580 MW Β· withdrawn
- Allegheny Energy Center LLCGas Β· 541 MW Β· withdrawn
- Gas project G06_W47, Allegheny CountyGas Β· 500 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem