SOLAR · PJM

Mountain Ridge Solar

Mountain Ridge Solar is a 40.0 MW solar request withdrawn in the PJM interconnection queue, in Somerset County, Pennsylvania, connecting to PENELEC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2025 (completed)
  2. Withdrawn / abandonedDec 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-201
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PENELEC
Developer
Mango Solar LLC
Connection point (POI)
Allegheny-New Baltimore 115kV
Location
Somerset County, Pennsylvania
Technology
Solar: 40.0 MW
Total requested
40.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
19 February 2025
Proposed online date
August 2023
Withdrawn
December 2025

Location

Marker shows the centre of Somerset County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania

Other requests in Somerset County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem