OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2012 requests) โ page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project 407, Sweetwater County Onshore wind |
79.8 MW | Withdrawn / abandoned |
| Onshore wind project 420-A, San Juan County Onshore wind |
79.2 MW | Withdrawn / abandoned |
| Magic Valley Chillers Gas ยท Calpine |
79.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-040, Kay County Onshore wind |
76.5 MW | Withdrawn / abandoned |
| Yuha Basin Solar Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project J243, Jackson County Onshore wind |
75.0 MW | Withdrawn / abandoned |
| Yermo Solar Solar |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-1212, Mccone County Onshore wind ยท Sand Creek Wind |
75.0 MW | Withdrawn / abandoned |
| TX_Marfa_Solar Solar ยท Lincoln Renewable Energy, LLC |
75.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-039, Custer County Onshore wind |
74.9 MW | Withdrawn / abandoned |
| Poplar Camp Onshore wind |
72.0 MW | Withdrawn / abandoned |
| Onshore wind project Y3-010, Centre County Onshore wind |
70.0 MW | Withdrawn / abandoned |
| Other project 236, Cherokee County Other |
70.0 MW | Withdrawn / abandoned |
| Onshore wind project Y2-016, Adams County Onshore wind |
68.0 MW | Withdrawn / abandoned |
| Gas project 406, Emery County Gas |
65.0 MW | Withdrawn / abandoned |
| Onshore wind project Y1-067, Wayne County Onshore wind |
64.6 MW | Withdrawn / abandoned |
| Battery storage project Y2-084, Tippecanoe County Battery storage |
64.0 MW | Withdrawn / abandoned |
| Other project Y2-086, Perry County Other |
62.5 MW | Withdrawn / abandoned |
| Winding Ridge Wind Farm Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
60.0 MW | Withdrawn / abandoned |
| Other project 117, Polk County Other ยท Masked |
58.4 MW | Withdrawn / abandoned |
| Horse Lake Onshore wind |
51.0 MW | Withdrawn / abandoned |
| Spruce Ridge Wind Farm Onshore wind |
50.8 MW | Withdrawn / abandoned |
| Solar project 436, Iron County Solar |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project Y1-016, Hardy County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project Y1-008, Accomack County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Solar project IC-265, Greene County Solar |
50.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-2012-2, Golden County Onshore wind |
50.0 MW | Withdrawn / abandoned |
| Backus Solar Energy Solar |
50.0 MW | Withdrawn / abandoned |
| Wellhead Power Nella CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Wellhead Power Lemietta CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Wellhead Power Woodland CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Wellhead Power Midfruit CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Onshore wind project J253, Woodbury County Onshore wind |
48.3 MW | Withdrawn / abandoned |
| Other project Y2-096, Frederick County Other |
47.2 MW | Withdrawn / abandoned |
| Onshore wind project 420-B, San Juan County Onshore wind ยท EDF Renewable Development, Inc |
45.6 MW | Withdrawn / abandoned |
| Tehachapi Valley Solar I Solar |
45.0 MW | Withdrawn / abandoned |
| KPP - 45 Gas |
45.0 MW | Withdrawn / abandoned |
| Solar Prime TX-2 Solar ยท Solar Prime LLC |
42.0 MW | Withdrawn / abandoned |
| Gas project Y2-110, Cape May County Gas |
40.0 MW | Withdrawn / abandoned |
| Gas project GEN-2012-008, Yoakum County Gas |
40.0 MW | Withdrawn / abandoned |
| SPS As 40MW PV Generation Facility Solar |
40.0 MW | Withdrawn / abandoned |
| Onshore wind project J252, Audubon County Onshore wind |
39.1 MW | Withdrawn / abandoned |
| Geothermal project G0477, Deschutes County Geothermal |
38.0 MW | Withdrawn / abandoned |
| Gas project Y2-053, Wood County Gas |
35.0 MW | Withdrawn / abandoned |
| Cape May Energy Center (CMEC) Gas |
34.0 MW | Withdrawn / abandoned |
| Troups Creek Wind Onshore wind ยท Ridgeline Energy, LLC |
32.0 MW | Withdrawn / abandoned |
| Alpine 1 Solar Solar ยท First Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project GEN-2012-022, Lea County Solar |
30.0 MW | Withdrawn / abandoned |
| Solar project GI-2012-6, Arapahoe County Solar |
30.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)111 ยท 19.3 GW
- CAISO (California)60 ยท 12.3 GW
- West (non-ISO utilities)95 ยท 9,460 MW
- Southeast (non-ISO utilities)36 ยท 9,047 MW
- ERCOT (Texas)24 ยท 6,711 MW
- MISO (Midcontinent)21 ยท 6,395 MW
- SPP (Southwest Power Pool)30 ยท 4,307 MW
- NYISO (New York)10 ยท 1,963 MW
- ISO-NE (New England)10 ยท 996 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)