πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Mississippi

SOLAR Β· SOUTHEAST

Solar project IC-265, Greene County

Solar project IC-265, Greene County is a 50.0 MW solar request withdrawn in the Southeast interconnection queue, in Greene County, Mississippi, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Feb 2012 (completed)
  2. Withdrawn / abandonedOct 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-265
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Leakesville 115 kV Substation
Location
Greene County, Mississippi
Technology
Solar: 50.0 MW
Total requested
50.0 MW
Service type
Network resource (NRIS)
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
13 February 2012
Withdrawn
October 2012

Location

Marker shows the centre of Greene County; the queue data does not give exact sites.

Power plants in Mississippi Β· Transmission lines in Mississippi

Other requests in Greene County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem