SOLAR Β· SOUTHEASTSolar project IC-265, Greene County
Solar project IC-265, Greene County is a 50.0 MW solar request withdrawn in the Southeast interconnection queue, in Greene County, Mississippi, connecting to Southern Company.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2012 (completed)
- Withdrawn / abandonedOct 2012 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- IC-265
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Leakesville 115 kV Substation
- Location
- Greene County, Mississippi
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 13 February 2012
- Withdrawn
- October 2012
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Greene County