United States βΊ Grid βΊ Interconnection queues βΊ Mississippi
SOLAR Β· MISOSolar project J709, Greene County
Solar project J709, Greene County is a 100 MW solar request withdrawn in the MISO interconnection queue, in Greene County, Mississippi, connecting to SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2016 (completed)
- Withdrawn / abandonedJan 2019 (project stopped here)
- ConsentedOct 2018 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J709
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- SOUTH MISSISSIPPI ELECTRIC POWER ASSOCIATION
- Connection point (POI)
- Green Substation 230kV
- Location
- Greene County, Mississippi
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: Withdrawn
- Queue status
- Withdrawn
- Entered queue
- 9 September 2016
- Agreement signed
- 17 October 2018
- Proposed online date
- April 2020
- Withdrawn
- January 2019
Location
Marker shows the centre of Greene County; the queue data does not give exact sites.
Power plants in Mississippi Β· Transmission lines in Mississippi
Other requests in Greene County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem