United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· ERCOT

Alpine 1 Solar

Alpine 1 Solar is a 30.0 MW solar request withdrawn in the ERCOT interconnection queue.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2012 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
14INR0026
Grid region
ERCOT (Texas)
Developer
First Solar
Connection point (POI)
tap 6666-6681 69kV
Technology
Solar: 30.0 MW
Total requested
30.0 MW
Study phase
FIS
Queue status
Withdrawn
Entered queue
25 April 2012
Proposed online date
December 2019

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem