SOLAR Β· CAISO

Yermo Solar

Yermo Solar is a 75.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to SCE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2012 (completed)
  2. Withdrawn / abandonedJun 2012 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
920
Grid region
CAISO (California)
Utility / transmission owner
SCE
Connection point (POI)
Coolwater-DunnSiding-Baker Substation 115kV
Location
Kern County, California
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 April 2012
Proposed online date
January 2015
Withdrawn
June 2012

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.