United States › Grid › Interconnection queues › Texas
OCTARY USA · INTERCONNECTION QUEUESQueue requests in study in Texas — page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Exergy Energy West Texas Natural Gas Reciprocating Power I Gas · August Partners LLC |
400 MW | In study |
| Biggs Solar Solar + storage · Biggs Solar Farm, LLC |
400 MW | In study |
| Springfield Solar Solar · BOULEVARD ASSOCIATES, LLC |
400 MW | In study |
| Boling Generation (TEF-Due Diligience) Gas · Boling Generation |
400 MW | In study |
| Solar project ERAS-2025-028, Hockley County Solar |
384 MW | In study |
| Moon Chapel Wind Onshore wind · Orsted Onshore Development North America, LLC |
379 MW | In study |
| Paint Rock Wind Onshore wind · Orsted Onshore Development North America, LLC |
379 MW | In study |
| Kilby1 Part 1 Small Block Simple Cycle Gas · Energy Forge One LLC |
371 MW | In study |
| Earthwise Solar Solar · Quanah Solar 2 |
371 MW | In study |
| Skyrider Wind Onshore wind · NextEra Energy Interconnection Holdings, LLC |
370 MW | In study |
| Viento Bravo Wind Onshore wind · Webb Wind, LLC |
367 MW | In study |
| Scott Crossing Solar SLF Solar + storage · FRESH AIR ENERGY II, LLC |
364 MW | In study |
| Channing Wind Onshore wind |
361 MW | Paused / redesign |
| Wildflower Storage Battery storage · Wildflower Storage LLC |
359 MW | In study |
| Tetris Solar Solar · NextEra Energy Interconnection Holdings LLC |
359 MW | In study |
| Tetris Solar (Alternative POI) Solar |
359 MW | Paused / redesign |
| Twinwood Solar 1 Solar · Twinwood PV1, LLC |
358 MW | In study |
| Green Ocelot Solar Solar + storage · Ocelot Solar LLC |
357 MW | In study |
| Funston Solar (AEP POI) Solar |
355 MW | Paused / redesign |
| Max 4 Wind Onshore wind · Lake Creek Wind, LLC |
353 MW | In study |
| Onshore wind project GEN-2020-067, Terry County Onshore wind |
353 MW | In study |
| Sombrero Solar Solar · Aurora Solar LLC |
352 MW | In study |
| Brookesmith Storage Battery storage · Brookesmith Storage LLC |
351 MW | In study |
| Solar + storage project GEN-2024-280, Andrews County Solar + storage |
350 MW | In study |
| HyFuels Green Lake Solar Solar · HyFuels Green Lake Solar LLC |
347 MW | In study |
| Solar project GEN-2024-046, Hansford County Solar |
345 MW | In study |
| Solar project GEN-2024-045, Hansford County Solar |
345 MW | In study |
| Rabbit Hollow Energy Storage Battery storage · Rabbit Hollow Energy Storage, LLC |
342 MW | In study |
| Titus Low Carbon Ventures Solar 1 Solar · Vaquero Solar, LLC |
338 MW | In study |
| Cielo Vista Power Gas Plant Gas · Cielo Vista Power, LLC |
335 MW | In study |
| River Boat Power Gas Plant Gas · Champion Creek Power, LLC |
334 MW | In study |
| Mountaineer Solar Solar · Mustang Mountaineer Solar LLC |
332 MW | In study |
| Andromeda Storage II Battery storage |
320 MW | Paused / redesign |
| Andromeda Storage IIB Battery storage |
320 MW | Paused / redesign |
| Radian Storage II Battery storage |
320 MW | Paused / redesign |
| Jade Thunder Storage Battery storage |
320 MW | Paused / redesign |
| Jade Flash Storage Battery storage |
320 MW | Paused / redesign |
| Radian Storage IIB Battery storage |
320 MW | Paused / redesign |
| White Bright BESS Battery storage · VLN, LLC |
314 MW | In study |
| Diablo Campo Storage Battery storage · Diablo Campo Energy Center, LLC |
314 MW | In study |
| Wild Paw Storage Battery storage · Wild Paw Energy Center, LLC |
313 MW | In study |
| Barkley Creek Solar Solar · 174 Power Global Properties, LLC |
312 MW | In study |
| Canyon Wind Alternative Onshore wind |
312 MW | Paused / redesign |
| Bulldog Power II Gas · Bulldog Power II LLC |
311 MW | In study |
| Bulldog Power (TEF - Due Diligence) Gas · Bulldog Power LLC |
311 MW | In study |
| Cielo Vista Storage Solar + storage · Cielo Vista Storage, LLC |
311 MW | In study |
| Royal River BESS Battery storage · Royal River LLC |
311 MW | In study |
| Prairie Branch BESS Solar + storage · Prairie Branch Energy, LLC |
310 MW | In study |
| Oak Tree Energy Storage Battery storage · Live Oak Energy Storage, LLC |
310 MW | In study |
| Cuhullin Wind Onshore wind |
310 MW | Paused / redesign |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- ERCOT (Texas)1,398 · 327.9 GW
- SPP (Southwest Power Pool)61 · 16.6 GW
- MISO (Midcontinent)22 · 6,012 MW
- West (non-ISO utilities)5 · 997 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)