United States › Grid › Interconnection queues › Illinois
OCTARY USA · INTERCONNECTION QUEUESWithdrawn queue requests in Illinois — page 5
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Battery storage project J3662, Monroe County Battery storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project H080, Carroll County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J1617, Vermilion County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J2349, Jackson County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project U2-003, Stephenson County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J1837, Shelby County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project U4-037, Dewitt County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project J2465, Logan County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project AH2-171, Kankakee County Solar |
200 MW | Withdrawn / abandoned |
| Battery storage project J2422, Washington County Battery storage |
200 MW | Withdrawn / abandoned |
| Battery storage project J2762, Tazewell County Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project J463, Montgomery County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project J1718, Vermilion County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project R29, Knox County Onshore wind |
200 MW | Withdrawn / abandoned |
| Battery storage project J3043, Tazewell County Battery storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project M09_CE28, Winnebago County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project O49, Winnebago County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J2427, Marion County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project AE2-153, Kankakee County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project AG1-005, Stephenson County Solar · Sky Yield Solar Farm, LLC |
200 MW | Withdrawn / abandoned |
| Onshore wind project J979, Christian County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar + storage project J3467, Mclean County Solar + storage |
200 MW | Withdrawn / abandoned |
| Solar project J1650, Logan County Solar |
200 MW | Withdrawn / abandoned |
| Solar project J3060, Perry County Solar |
200 MW | Withdrawn / abandoned |
| Solar project AG1-379, Woodford County Solar · Minonk Solar, LLC |
200 MW | Withdrawn / abandoned |
| Battery storage project J2426, Marion County Battery storage |
200 MW | Withdrawn / abandoned |
| Onshore wind project J107, Logan County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project AA1-086, Macon County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project AH1-297, Stark County Onshore wind · Invenergy Wind Development LLC |
200 MW | Withdrawn / abandoned |
| Onshore wind project Z2-086, Adams County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J2463, Washington County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project H079, Adams County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project J1204, Cumberland County Solar |
199 MW | Withdrawn / abandoned |
| Other project AF2-201, Stephenson County Other · Blue Violet Energy, LLC |
199 MW | Withdrawn / abandoned |
| Bison Meadows Wind Project Onshore wind · Bison Meadows Wind Project, LLC |
199 MW | Withdrawn / abandoned |
| Solar project J2645, St. Clair County Solar |
199 MW | Withdrawn / abandoned |
| Solar project J1771, Cumberland County Solar |
197 MW | Withdrawn / abandoned |
| Onshore wind project AG1-403, Mclean County Onshore wind |
188 MW | Withdrawn / abandoned |
| Onshore wind project AD2-159, Macon County Onshore wind |
188 MW | Withdrawn / abandoned |
| Replacing 179 MW Coal with 179 MW Solar; Edwards Unit 3 Other |
185 MW | Withdrawn / abandoned |
| Ramble Wind Onshore wind · Ramble Wind Energy LLC |
180 MW | Withdrawn / abandoned |
| Solar project J3174, Scott County Solar |
180 MW | Withdrawn / abandoned |
| Solar project AF1-012, Lee County Solar |
175 MW | Withdrawn / abandoned |
| Solar project AH1-232, Winnebago County Solar |
175 MW | Withdrawn / abandoned |
| Onshore wind project J3239, Christian County Onshore wind |
175 MW | Withdrawn / abandoned |
| Onshore wind project AG1-434, Lee County Onshore wind · RWE Renewables Development, LLC |
175 MW | Withdrawn / abandoned |
| Onshore wind project L13_CE26, Lasalle County Onshore wind |
175 MW | Withdrawn / abandoned |
| Onshore wind project J034, Logan County Onshore wind |
175 MW | Withdrawn / abandoned |
| Other project G061, Jackson County Other |
165 MW | Withdrawn / abandoned |
| Onshore wind project J108, Ford County Onshore wind |
165 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)