πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

SOLAR Β· PJM

Solar project AG1-005, Stephenson County

Solar project AG1-005, Stephenson County is a 200 MW solar request withdrawn in the PJM interconnection queue, in Stephenson County, Illinois, connecting to ComEd.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2020 (completed)
  2. Withdrawn / abandonedJan 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AG1-005
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ComEd
Developer
Sky Yield Solar Farm, LLC
Connection point (POI)
Corbin-Crescent Ridge 138 kV
Location
Stephenson County, Illinois
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study
Queue status
Withdrawn
Entered queue
29 April 2020
Proposed online date
October 2023
Withdrawn
January 2025

Location

Marker shows the centre of Stephenson County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Stephenson County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem