Onshore wind project J034, Logan County

Onshore wind project J034, Logan County is a 175 MW onshore wind request withdrawn in the MISO interconnection queue, in Logan County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2009 (completed)
  2. Withdrawn / abandonedJan 2017 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J034
Grid region
MISO (Midcontinent)
Connection point (POI)
Fogarty 138 kV Substation
Location
Logan County, Illinois
Technology
Wind: 175 MW
Total requested
175 MW
Study phase
Network Upgrade
Queue status
Withdrawn
Entered queue
12 March 2009
Agreement signed
10 August 2012
Proposed online date
November 2010
Withdrawn
January 2017

Location

Marker shows the centre of Logan County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Logan County