United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · PJMBison Meadows Wind Project
Bison Meadows Wind Project is a 199 MW onshore wind request withdrawn in the PJM interconnection queue, in Lee County, Illinois, connecting to ComEd.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2020 (completed)
- Withdrawn / abandonedNov 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AF2-392
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ComEd
- Developer
- Bison Meadows Wind Project, LLC
- Connection point (POI)
- Nelson-Dixon 138 kV
- Location
- Lee County, Illinois
- Technology
- Wind: 199 MW
- Total requested
- 199 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 31 March 2020
- Proposed online date
- September 2024
- Withdrawn
- November 2025
Location
Marker shows the centre of Lee County; the queue data does not give exact sites.
Other requests in Lee County
- Shady Oaks Wind Power ProjectOnshore wind · 106 MW · agreement signed
- Steward Creek SolarSolar · 300 MW · in study
- South Dixon SolarSolar · 300 MW · in study
- Solar project AH1-151, Lee CountySolar · 200 MW · in study
- Solar project AH1-150, Lee CountySolar · 200 MW · in study
- Steward Creek SolarSolar · 200 MW · in study
- South Dixon SolarSolar · 200 MW · in study
- Solar project AH1-044, Lee CountySolar · 200 MW · in study
- Solar project AH1-338, Lee CountySolar · 180 MW · in study
- Battery storage project AH2-015, Lee CountyBattery storage · 110 MW · in study
- Steward Creek SolarSolar · 100 MW · in study
- Battery storage project AH2-123, Lee CountyBattery storage · 100 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem