Completed queue projects in MISO (Midcontinent) — page 5

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown51469.7 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

514 requests · page 5 of 11
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J191, Cass County
Onshore wind
101 MWOperating Cass, IAMISO Dec 20102012
Onshore wind project G426, Jackson County
Onshore wind
101 MWOperating Jackson, MNMISO May 20042007
Onshore wind project J301, Tuscola County
Onshore wind
101 MWOperating Tuscola, MIMISO Nov 20132017
Onshore wind project J202, Tuscola County
Onshore wind
101 MWOperating Tuscola, MIMISO Feb 20112014
Onshore wind project J513, White County
Onshore wind
100 MWOperating White, INMISO Nov 20152020
Onshore wind project J826, Mclean County
Onshore wind
100 MWOperating Mclean, ILMISO Jun 20172021
Onshore wind project G386, Martin County
Onshore wind
100 MWOperating Martin, MNMISO Dec 20032007
Onshore wind project MPC02100, Oliver County
Onshore wind
100 MWOperating Oliver, NDMISO Dec 20082016
Onshore wind project G176, Lincoln County
Onshore wind
100 MWOperating Lincoln, MNMISO Mar 20022005
Solar project J893, White County
Solar
100 MWOperating White, ARMISO Jun 20172021
Onshore wind project G060, Murray County
Onshore wind
100 MWOperating Murray, MNMISO Sep 20002001
Onshore wind project G424, St. Louis County
Onshore wind
100 MWOperating St. Louis, MNMISO Apr 20042005
Onshore wind project R41, Adair County
Onshore wind
100 MWOperating Adair, IAMISO Apr 20072009
Solar project J620, Chicot County
Solar
100 MWOperating Chicot, ARMISO May 20162019
Solar project J1372, Pointe Coupee Parish County
Solar
100 MWOperating Pointe Coupee Parish, LAMISO Apr 20192023
Solar project J830, Madison County
Solar
100 MWOperating Madison, MSMISO Jun 20172021
Onshore wind project R23, Crawford County
Onshore wind
100 MWOperating Crawford, IAMISO Sep 2005target 2012
Onshore wind project J340, Huron County
Onshore wind
100 MWOperating Huron, MIMISO May 20142016
Onshore wind project J431, Benton County
Onshore wind
100 MWOperating Benton, INMISO Dec 20142017
Onshore wind project J052, Bay County
Onshore wind
100 MWOperating Bay, MIMISO Jul 20092011
Solar project J679, Carroll County
Solar
100 MWOperating Carroll, MSMISO Jul 20162021
Solar project J385, Chisago County
Solar
100 MWOperating Chisago, MNMISO Sep 20142016
Onshore wind project J262, Stutsman County
Onshore wind
100 MWOperating Stutsman, NDMISO Jan 20132014
Onshore wind project G298, Dickinson County
Onshore wind
100 MWOperating Dickinson, IAMISO Feb 20032010
Onshore wind project N001, Benton County
Onshore wind
100 MWOperating Benton, INMISO Jan 20032008
Solar project J834, Phillips County
Solar
100 MWOperating Phillips, ARMISO Jun 20172021
Onshore wind project J715, Marshall County
Onshore wind
100 MWOperating Marshall, ILMISO Jun 20172021
Onshore wind project J263, Stutsman County
Onshore wind
100 MWOperating Stutsman, NDMISO Jan 20132014
Onshore wind project G255, Brookings County
Onshore wind
100 MWOperating Brookings, SDMISO Sep 20022006
Solar project J1434, Monroe County
Solar
100 MWOperating Monroe, ARMISO Apr 20192024
Onshore wind project J274, Madison County
Onshore wind
100 MWOperating Madison, IAMISO Mar 20132014
Solar project J663, Phillips County
Solar
100 MWOperating Phillips, ARMISO Jun 20172022
Onshore wind project G439, Benton County
Onshore wind
100 MWOperating Benton, INMISO Jul 20042005
Onshore wind project J426, Pipestone County
Onshore wind
100 MWOperating Pipestone, MNMISO Nov 20142018
Onshore wind project J752, Tuscola County
Onshore wind
100 MWOperating Tuscola, MIMISO Nov 20162019
Onshore wind project G515, Tazewell County
Onshore wind
100 MWOperating Tazewell, ILMISO Apr 20052007
Onshore wind project G706, Columbia County
Onshore wind
99.0 MWOperating Columbia, WIMISO Nov 20062008
Onshore wind project G947, Franklin County
Onshore wind
99.0 MWOperating Franklin, IAMISO Jan 20082011
Onshore wind project H094, Vermilion County
Onshore wind
99.0 MWOperating Vermilion, ILMISO Jul 20082010
Solar project J811, Fayette County
Solar
99.0 MWOperating Fayette, ILMISO Jun 20172021
Onshore wind project G830, Mchenry County
Onshore wind
99.0 MWOperating Mchenry, NDMISO Jul 20072010
Solar project J1002, Waushara County
Solar
99.0 MWOperating Waushara, WIMISO Mar 20182023
Gas project J200, Morton County
Gas
99.0 MWOperating Morton, NDMISO Feb 20112016
Onshore wind project MPC00100, Cavalier County
Onshore wind
99.0 MWOperating Cavalier, NDMISO Sep 20062007
Solar project J505, Manitowoc County
Solar
99.0 MWOperating Manitowoc, WIMISO Nov 20152021
Onshore wind project G551, Howard County
Onshore wind
99.0 MWOperating Howard, IAMISO Sep 20052006
Solar project J808, Randolph County
Solar
99.0 MWOperating Randolph, ILMISO Jun 20172020
Onshore wind project J503, Emmons County
Onshore wind
98.8 MWOperating Emmons, NDMISO Nov 20152019
Onshore wind project J432, Brookings County
Onshore wind
98.0 MWOperating Brookings, SDMISO Dec 20142019
Onshore wind project J652, Lafayette County
Onshore wind
98.0 MWOperating Lafayette, WIMISO Jul 20162017
Page 5 of 11

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)