United States › Grid › Interconnection queues › Illinois
ONSHORE WIND · MISOOnshore wind project J826, Mclean County
Onshore wind project J826, Mclean County is a 100 MW onshore wind request built and operating in the MISO interconnection queue, in Mclean County, Illinois, connecting to AMEREN ILLINOIS.
Request details
- Queue ID
- J826
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMEREN ILLINOIS
- Connection point (POI)
- Weedman Substation 138kV Bus
- Location
- Mclean County, Illinois
- Technology
- Wind: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 16 June 2017
- Agreement signed
- 17 December 2019
- Proposed online date
- May 2021
- Came online
- May 2021
Location
Marker shows the centre of Mclean County; the queue data does not give exact sites.
Other requests in Mclean County
- Twin Groves Storage IIBattery storage · 50.0 MW · agreement signed
- Twin Groves Storage IBattery storage · 50.0 MW · agreement signed
- Surplus; G876/G877Wind + storage · 400 MW · in study
- Onshore wind project J3991, Mclean CountyOnshore wind · 340 MW · in study
- Battery storage project AI1-024, Mclean CountyBattery storage · 300 MW · in study
- Onshore wind project J3681, Mclean CountyOnshore wind · 300 MW · in study
- Dawson SolarSolar · 300 MW · in study
- Battery storage project J4118, Mclean CountyBattery storage · 250 MW · in study
- Battery storage project AI1-023, Mclean CountyBattery storage · 200 MW · in study
- Onshore wind project J3566, Mclean CountyOnshore wind · 198 MW · in study
- Bright Stalk Generating FacilityOnshore wind · 150 MW · in study
- Bright Stalk Generating FacilitySolar · 150 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem