United States › Grid › Interconnection queues › Mississippi
SOLAR · MISOSolar project J679, Carroll County
Solar project J679, Carroll County is a 100 MW solar request built and operating in the MISO interconnection queue, in Carroll County, Mississippi, connecting to Entergy.
Request details
- Queue ID
- J679
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- Entergy
- Connection point (POI)
- Greenwood - Winona 115kV
- Location
- Carroll County, Mississippi
- Technology
- Solar: 100 MW
- Total requested
- 100 MW
- Service type
- Network resource (NRIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 11 July 2016
- Agreement signed
- 12 October 2018
- Proposed online date
- April 2021
- Came online
- April 2021
Location
Marker shows the centre of Carroll County; the queue data does not give exact sites.
Power plants in Mississippi · Transmission lines in Mississippi
Other requests in Carroll County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem