United States › Grid › Interconnection queues › North Dakota
ONSHORE WIND · MISOOnshore wind project G830, Mchenry County
Onshore wind project G830, Mchenry County is a 99.0 MW onshore wind request built and operating in the MISO interconnection queue, in Mchenry County, North Dakota.
Request details
- Queue ID
- G830
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- GRE McHenry substation
- Location
- Mchenry County, North Dakota
- Technology
- Wind: 99.0 MW
- Total requested
- 99.0 MW
- Study phase
- DPP - SIS
- Queue status
- Operational
- Entered queue
- 30 July 2007
- Agreement signed
- 20 September 2012
- Proposed online date
- August 2010
- Came online
- August 2010
Location
Marker shows the centre of Mchenry County; the queue data does not give exact sites.
Power plants in North Dakota · Transmission lines in North Dakota
Other requests in Mchenry County
- Onshore wind project G408, Mchenry CountyOnshore wind · 12.0 MW · built
- Onshore wind project GI-0707, Mchenry CountyOnshore wind · 242 MW · withdrawn
- Onshore wind project J746, Mchenry CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project J1754, Mchenry CountyOnshore wind · 200 MW · withdrawn
- Onshore wind project G328, Mchenry CountyOnshore wind · 12.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem