United States › Grid › Interconnection queues › Iowa
ONSHORE WIND · MISOOnshore wind project J191, Cass County
Onshore wind project J191, Cass County is a 101 MW onshore wind request built and operating in the MISO interconnection queue, in Cass County, Iowa.
Request details
- Queue ID
- J191
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Rolling Hills 345 kV Substation
- Location
- Cass County, Iowa
- Technology
- Wind: 101 MW
- Total requested
- 101 MW
- Study phase
- Network Upgrade
- Queue status
- Operational
- Entered queue
- 28 December 2010
- Agreement signed
- 4 May 2015
- Proposed online date
- September 2012
- Came online
- September 2012
Location
Marker shows the centre of Cass County; the queue data does not give exact sites.
Other requests in Cass County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem