United States โบ Grid โบ Interconnection queues
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in the USA (2012 requests) โ page 4
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Onshore wind project 4907, Carteret County Onshore wind ยท Masked |
120 MW | Withdrawn / abandoned |
| Nuclear project GEN-2012-017, Nemaha County Nuclear |
115 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-023, Barber County Onshore wind |
115 MW | Withdrawn / abandoned |
| SSE phase 1 Onshore wind ยท Spinning Star Energy LLC |
112 MW | Withdrawn / abandoned |
| Onshore wind project 36, Whitman County Onshore wind |
105 MW | Withdrawn / abandoned |
| Onshore wind project Y1-031, Clarion County Onshore wind |
102 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-002, Scott County Onshore wind |
101 MW | Withdrawn / abandoned |
| Other project 235, Cherokee County Other |
101 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-029, Kiowa County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project Y2-010, White County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J260, Ford County Onshore wind |
100 MW | Withdrawn / abandoned |
| Solar project G0479, Lake County Solar |
100 MW | Withdrawn / abandoned |
| Lucerne Valley 100 MW PV Plant Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project IC-268, Etowah County Onshore wind |
100 MW | Withdrawn / abandoned |
| Lucerne Solar Energy - C5 Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project J265, Marshall County Onshore wind |
100 MW | Withdrawn / abandoned |
| Gas project GEN-2012-026, Thomas County Gas |
100 MW | Withdrawn / abandoned |
| Onshore wind project J261, Montgomery County Onshore wind |
100 MW | Withdrawn / abandoned |
| Dunnigan Hills Onshore wind |
100 MW | Withdrawn / abandoned |
| Los Robles Solar |
100 MW | Withdrawn / abandoned |
| Onshore wind project Y1-030, Wyandot County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project J245, Tuscola County Onshore wind |
100 MW | Withdrawn / abandoned |
| Onshore wind project Y1-032, Potter County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-1209, Charles Mix County Onshore wind ยท Pioneer Energy |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-1214, Brown County Onshore wind ยท Day County Wind II |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project Y1-029, Accomack County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-013, Gray County Onshore wind |
99.0 MW | Withdrawn / abandoned |
| Onshore wind project 441, Umatilla County Onshore wind |
98.9 MW | Withdrawn / abandoned |
| Onshore wind project 411, Umatilla County Onshore wind |
98.4 MW | Withdrawn / abandoned |
| South Pier Improvement Gas ยท Astoria Generating Co. |
95.5 MW | Withdrawn / abandoned |
| Hidalgo Chillers Gas ยท Calpine |
95.0 MW | Withdrawn / abandoned |
| Berrians East Replacement Gas ยท NRG Berrians East Development, LLC |
94.2 MW | Withdrawn / abandoned |
| Downeast Wind Onshore wind |
90.0 MW | Withdrawn / abandoned |
| Onshore wind project IC-267, Cleburne County Onshore wind |
89.0 MW | Withdrawn / abandoned |
| Wind Onshore wind |
84.0 MW | Withdrawn / abandoned |
| Onshore wind project GEN-2012-005, Knox County Onshore wind |
81.0 MW | Withdrawn / abandoned |
| Onshore wind project 416, San Juan County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project 435, Crook County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project GI-1210, Blaine County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project 448, Crook County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 148, Stillwater County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 427, Sweetwater County Onshore wind ยท OM Power 1, LLC |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 440, Carbon County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Solar project 447, Crook County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project 434, Crook County Solar |
80.0 MW | Withdrawn / abandoned |
| Belridge Solar Energy 2 Project Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 418, San Juan County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Newhall Solar Energy Project Solar |
80.0 MW | Withdrawn / abandoned |
| Paragon Wind Onshore wind ยท Clipper Wind Power Development |
79.9 MW | Withdrawn / abandoned |
| Onshore wind project 426, San Juan County Onshore wind |
79.9 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- PJM (Mid-Atlantic, Midwest)111 ยท 19.3 GW
- CAISO (California)60 ยท 12.3 GW
- West (non-ISO utilities)95 ยท 9,460 MW
- Southeast (non-ISO utilities)36 ยท 9,047 MW
- ERCOT (Texas)24 ยท 6,711 MW
- MISO (Midcontinent)21 ยท 6,395 MW
- SPP (Southwest Power Pool)30 ยท 4,307 MW
- NYISO (New York)10 ยท 1,963 MW
- ISO-NE (New England)10 ยท 996 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)