ONSHORE WIND Β· SPP

Onshore wind project GEN-2012-002, Scott County

Onshore wind project GEN-2012-002, Scott County is a 101 MW onshore wind request withdrawn in the SPP interconnection queue, in Scott County, Kansas, connecting to SUNC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Mar 2012 (completed)
  2. Withdrawn / abandonedDec 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GEN-2012-002
Grid region
SPP (Southwest Power Pool)
Utility / transmission owner
SUNC
Connection point (POI)
Tap Pile - Scott City 115kV
Location
Scott County, Kansas
Technology
Wind: 101 MW
Total requested
101 MW
Service type
Energy only (ERIS)
Study phase
WITHDRAWN
Queue status
Withdrawn
Entered queue
22 March 2012
Proposed online date
January 2014
Withdrawn
December 2013

Location

Marker shows the centre of Scott County; the queue data does not give exact sites.