United States › Grid › Interconnection queues › Ohio

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Ohio — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown59480.2 GW
Active in queue19.7 GW185 requests
Agreement signed8,251 MW65 requests
Withdrawn59480.2 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

594 requests · page 4 of 12
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project AF2-216, Union County
Solar
150 MWWithdrawn / abandoned Union, OHPJM Mar 2020target 2024
Battery storage project AH1-579, Union County
Battery storage
150 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2028
Leipsic Wind Project
Onshore wind
150 MWWithdrawn / abandoned Putnam, OHPJM May 2009target 2021
Muskingum Solar
Solar
150 MWWithdrawn / abandoned Muskingum, OHPJM Apr 2017target 2023
Solar + storage project AH1-449, Washington County
Solar + storage
150 MWWithdrawn / abandoned Washington, OHPJM Sep 2021target 2025
Solar project AI2-438, Knox County
Solar
150 MWWithdrawn / abandoned Knox, OHPJM Mar 2023target 2027
Onshore wind project X2-058, Hancock County
Onshore wind
150 MWWithdrawn / abandoned Hancock, OHPJM Jun 2011target 2012
Solar project AF2-321, Williams County
Solar · Williams County Solar, LLC
148 MWWithdrawn / abandoned Williams, OHPJM Mar 2020target 2023
Solar + storage project AH1-764, Williams County
Solar + storage · Williams County Solar, LLC
148 MWWithdrawn / abandoned Williams, OHPJM target 2029
Solar project AF2-209, Defiance County
Solar · Mink Solar LLC
140 MWWithdrawn / abandoned Defiance, OHPJM Mar 2020target 2023
Battery storage project AH1-767, Hardin County
Battery storage · RWE Solar Development, LLC
140 MWWithdrawn / abandoned Hardin, OHPJM target 2028
Coal project T152, Scioto County
Coal
140 MWWithdrawn / abandoned Scioto, OHPJM Jan 2008target 2011
Battery storage project AE2-331, Defiance County
Battery storage
139 MWWithdrawn / abandoned Defiance, OHPJM Mar 2019target 2021
Solar project AI1-104, Paulding County
Solar
135 MWWithdrawn / abandoned Paulding, OHPJM Aug 2022target 2029
Gas project H023, Lucas County
Gas
135 MWWithdrawn / abandoned Lucas, OHMISO May 2008target 2012
FDS Coke Plant
Other
135 MWWithdrawn / abandoned Lucas, OHPJM May 2008target 2017
Gas project W1-058A_DK1, Butler County
Gas
135 MWWithdrawn / abandoned Butler, OHPJM Mar 2010target 2012
Gas project J120, Butler County
Gas
135 MWWithdrawn / abandoned Butler, OHMISO Mar 2010target 2010
Solar + storage project AH1-539, Hardin County
Solar + storage · Riverlake Energy, LLC
129 MWWithdrawn / abandoned Hardin, OHPJM Mar 2025target 2025
Solar + storage project AG2-355, Morgan County
Solar + storage · IRGAH Renewables Development LLC
125 MWWithdrawn / abandoned Morgan, OHPJM Mar 2021target 2024
Battery storage project AG2-359, Brown County
Battery storage
125 MWWithdrawn / abandoned Brown, OHPJM Mar 2021target 2024
Cadence Solar II Energy Center
Solar
120 MWWithdrawn / abandoned Union, OHPJM Mar 2018target 2026
Solar project AH1-520, Union County
Solar
120 MWWithdrawn / abandoned Union, OHPJM Sep 2021target 2024
Solar project AF2-124, Highland County
Solar
120 MWWithdrawn / abandoned Highland, OHPJM Feb 2020target 2023
Solar project AC1-023, Allen County
Solar
120 MWWithdrawn / abandoned Allen, OHPJM Jul 2016target 2017
Onshore wind project N38, Hardin County
Onshore wind
120 MWWithdrawn / abandoned Hardin, OHPJM Jan 2005target 2006
Solar + storage project AH2-147, Logan County
Solar + storage
119 MWWithdrawn / abandoned Logan, OHPJM Mar 2022target 2027
Solar project AH2-212, Madison County
Solar
115 MWWithdrawn / abandoned Madison, OHPJM Mar 2022target 2026
Solar project AC2-064, Highland County
Solar
115 MWWithdrawn / abandoned Highland, OHPJM Feb 2017target 2019
Scioto Farms Solar Project
Solar
110 MWWithdrawn / abandoned Pickaway, OHPJM Mar 2018target 2025
Solar project AH1-550, Licking County
Solar
110 MWWithdrawn / abandoned Licking, OHPJM Sep 2021target 2025
Battery storage project AH1-598, Ashland County
Battery storage
110 MWWithdrawn / abandoned Ashland, OHPJM Sep 2021target 2025
Solar project AH1-597, Ashland County
Solar
110 MWWithdrawn / abandoned Ashland, OHPJM Sep 2021target 2025
Solar project AG2-018, Morgan County
Solar
105 MWWithdrawn / abandoned Morgan, OHPJM Oct 2020target 2022
Gas project AF2-012, Montgomery County
Gas
104 MWWithdrawn / abandoned Montgomery, OHPJM Oct 2019target 2021
Gas project AE2-296, Montgomery County
Gas
104 MWWithdrawn / abandoned Montgomery, OHPJM Mar 2019target 2020
Onshore wind project H091, Trumbull County
Onshore wind
101 MWWithdrawn / abandoned Trumbull, OHMISO Jul 2008target 2011
Onshore wind project G756, Logan County
Onshore wind
101 MWWithdrawn / abandoned Logan, OHMISO Feb 2007target 2009
Solar project AF1-035, Highland County
Solar
100 MWWithdrawn / abandoned Highland, OHPJM May 2019target 2021
Solar project AG1-042, Franklin County
Solar
100 MWWithdrawn / abandoned Franklin, OHPJM Jun 2020target 2023
Solar project AH2-275, Carroll County
Solar
100 MWWithdrawn / abandoned Carroll, OHPJM Mar 2022target 2023
Solar + storage project AH1-538, Van Wert County
Solar + storage · Riverlake Energy, LLC
100 MWWithdrawn / abandoned Van Wert, OHPJM Sep 2021target 2025
Battery storage project AH2-274, Union County
Battery storage
100 MWWithdrawn / abandoned Union, OHPJM Mar 2022target 2026
Solar project AF1-076, Allen County
Solar
100 MWWithdrawn / abandoned Allen, OHPJM Aug 2019target 2021
Battery storage project AH2-219, Pickaway County
Battery storage
100 MWWithdrawn / abandoned Pickaway, OHPJM Mar 2022target 2026
Hayden Run
Solar
100 MWWithdrawn / abandoned Franklin, OHPJM Sep 2019target 2023
Solar project AE1-030, Montgomery County
Solar
100 MWWithdrawn / abandoned Montgomery, OHPJM Jun 2018target 2021
Solar project AD2-146, Butler County
Solar
100 MWWithdrawn / abandoned Butler, OHPJM Mar 2018target 2020
Solar project AC2-041, Highland County
Solar
100 MWWithdrawn / abandoned Highland, OHPJM Feb 2017target 2019
Ripley Solar II
Solar
100 MWWithdrawn / abandoned Fairfield, OHPJM Sep 2020target 2027
Page 4 of 12

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)