| Project | Capacity | Status |
|---|---|---|
| Solar project AF2-216, Union County Solar |
150 MW | Withdrawn / abandoned |
| Battery storage project AH1-579, Union County Battery storage |
150 MW | Withdrawn / abandoned |
| Leipsic Wind Project Onshore wind |
150 MW | Withdrawn / abandoned |
| Muskingum Solar Solar |
150 MW | Withdrawn / abandoned |
| Solar + storage project AH1-449, Washington County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar project AI2-438, Knox County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project X2-058, Hancock County Onshore wind |
150 MW | Withdrawn / abandoned |
| Solar project AF2-321, Williams County Solar · Williams County Solar, LLC |
148 MW | Withdrawn / abandoned |
| Solar + storage project AH1-764, Williams County Solar + storage · Williams County Solar, LLC |
148 MW | Withdrawn / abandoned |
| Solar project AF2-209, Defiance County Solar · Mink Solar LLC |
140 MW | Withdrawn / abandoned |
| Battery storage project AH1-767, Hardin County Battery storage · RWE Solar Development, LLC |
140 MW | Withdrawn / abandoned |
| Coal project T152, Scioto County Coal |
140 MW | Withdrawn / abandoned |
| Battery storage project AE2-331, Defiance County Battery storage |
139 MW | Withdrawn / abandoned |
| Solar project AI1-104, Paulding County Solar |
135 MW | Withdrawn / abandoned |
| Gas project H023, Lucas County Gas |
135 MW | Withdrawn / abandoned |
| FDS Coke Plant Other |
135 MW | Withdrawn / abandoned |
| Gas project W1-058A_DK1, Butler County Gas |
135 MW | Withdrawn / abandoned |
| Gas project J120, Butler County Gas |
135 MW | Withdrawn / abandoned |
| Solar + storage project AH1-539, Hardin County Solar + storage · Riverlake Energy, LLC |
129 MW | Withdrawn / abandoned |
| Solar + storage project AG2-355, Morgan County Solar + storage · IRGAH Renewables Development LLC |
125 MW | Withdrawn / abandoned |
| Battery storage project AG2-359, Brown County Battery storage |
125 MW | Withdrawn / abandoned |
| Cadence Solar II Energy Center Solar |
120 MW | Withdrawn / abandoned |
| Solar project AH1-520, Union County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AF2-124, Highland County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AC1-023, Allen County Solar |
120 MW | Withdrawn / abandoned |
| Onshore wind project N38, Hardin County Onshore wind |
120 MW | Withdrawn / abandoned |
| Solar + storage project AH2-147, Logan County Solar + storage |
119 MW | Withdrawn / abandoned |
| Solar project AH2-212, Madison County Solar |
115 MW | Withdrawn / abandoned |
| Solar project AC2-064, Highland County Solar |
115 MW | Withdrawn / abandoned |
| Scioto Farms Solar Project Solar |
110 MW | Withdrawn / abandoned |
| Solar project AH1-550, Licking County Solar |
110 MW | Withdrawn / abandoned |
| Battery storage project AH1-598, Ashland County Battery storage |
110 MW | Withdrawn / abandoned |
| Solar project AH1-597, Ashland County Solar |
110 MW | Withdrawn / abandoned |
| Solar project AG2-018, Morgan County Solar |
105 MW | Withdrawn / abandoned |
| Gas project AF2-012, Montgomery County Gas |
104 MW | Withdrawn / abandoned |
| Gas project AE2-296, Montgomery County Gas |
104 MW | Withdrawn / abandoned |
| Onshore wind project H091, Trumbull County Onshore wind |
101 MW | Withdrawn / abandoned |
| Onshore wind project G756, Logan County Onshore wind |
101 MW | Withdrawn / abandoned |
| Solar project AF1-035, Highland County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AG1-042, Franklin County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AH2-275, Carroll County Solar |
100 MW | Withdrawn / abandoned |
| Solar + storage project AH1-538, Van Wert County Solar + storage · Riverlake Energy, LLC |
100 MW | Withdrawn / abandoned |
| Battery storage project AH2-274, Union County Battery storage |
100 MW | Withdrawn / abandoned |
| Solar project AF1-076, Allen County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project AH2-219, Pickaway County Battery storage |
100 MW | Withdrawn / abandoned |
| Hayden Run Solar |
100 MW | Withdrawn / abandoned |
| Solar project AE1-030, Montgomery County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AD2-146, Butler County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AC2-041, Highland County Solar |
100 MW | Withdrawn / abandoned |
| Ripley Solar II Solar |
100 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)