United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR + STORAGE Β· PJMSolar + storage project AH1-764, Williams County
Solar + storage project AH1-764, Williams County is a 148 MW solar + storage request withdrawn in the PJM interconnection queue, in Williams County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- Planning (completed)
- Withdrawn / abandonedMay 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-764
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Developer
- Williams County Solar, LLC
- Location
- Williams County, Ohio
- Technology
- Solar: 148 MW Β· Battery
- Total requested
- 148 MW
- Service type
- Network resource (NRIS)
- Study phase
- In Progress (unknown study)
- Queue status
- Withdrawn
- Proposed online date
- July 2029
- Withdrawn
- May 2025
Location
Marker shows the centre of Williams County; the queue data does not give exact sites.
Other requests in Williams County
- Other project L004, Williams CountyOther Β· -22.0 MW Β· in study
- Montpelier SolarSolar Β· 49.0 MW Β· built
- Solar project AF2-321, Williams CountySolar Β· 148 MW Β· withdrawn
- Solar project AG1-056, Williams CountySolar Β· 54.0 MW Β· withdrawn
- Solar project AG2-377, Williams CountySolar Β· 20.0 MW Β· withdrawn
- Solar project AF2-386, Williams CountySolar Β· 15.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem