United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR + STORAGE Β· PJM

Solar + storage project AH1-764, Williams County

Solar + storage project AH1-764, Williams County is a 148 MW solar + storage request withdrawn in the PJM interconnection queue, in Williams County, Ohio, connecting to ATSI.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-764
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
ATSI
Developer
Williams County Solar, LLC
Location
Williams County, Ohio
Technology
Solar: 148 MW Β· Battery
Total requested
148 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Proposed online date
July 2029
Withdrawn
May 2025

Location

Marker shows the centre of Williams County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Williams County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem