United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

BATTERY STORAGE Β· PJM

Battery storage project AH1-767, Hardin County

Battery storage project AH1-767, Hardin County is a 140 MW battery storage request withdrawn in the PJM interconnection queue, in Hardin County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. Planning (completed)
  2. Withdrawn / abandonedMay 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-767
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
RWE Solar Development, LLC
Location
Hardin County, Ohio
Technology
Battery: 140 MW
Total requested
140 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Proposed online date
August 2028
Withdrawn
May 2025

Location

Marker shows the centre of Hardin County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Hardin County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem