πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Ohio

SOLAR + STORAGE Β· PJM

Solar + storage project AH1-538, Van Wert County

Solar + storage project AH1-538, Van Wert County is a 100 MW solar + storage request withdrawn in the PJM interconnection queue, in Van Wert County, Ohio, connecting to AEP.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2021 (completed)
  2. Withdrawn / abandonedJul 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
AH1-538
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
AEP
Developer
Riverlake Energy, LLC
Connection point (POI)
East Lima - Haviland 138 kV
Location
Van Wert County, Ohio
Technology
Solar: 100 MW Β· Battery
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
In Progress (unknown study)
Queue status
Withdrawn
Entered queue
10 September 2021
Proposed online date
March 2025
Withdrawn
July 2025

Location

Marker shows the centre of Van Wert County; the queue data does not give exact sites.

Power plants in Ohio Β· Transmission lines in Ohio

Other requests in Van Wert County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem