SOLAR Β· PJMSolar project AC1-023, Allen County
Solar project AC1-023, Allen County is a 120 MW solar request withdrawn in the PJM interconnection queue, in Allen County, Ohio, connecting to AEP.
Queue statusWithdrawn / abandoned
- PlanningQueued Jul 2016 (completed)
- Withdrawn / abandonedAug 2016 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AC1-023
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- AEP
- Connection point (POI)
- Southwest Lima-East Lima 345kV
- Location
- Allen County, Ohio
- Technology
- Solar: 120 MW
- Total requested
- 120 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 14 July 2016
- Proposed online date
- December 2017
- Withdrawn
- August 2016
Location
Marker shows the centre of Allen County; the queue data does not give exact sites.
Other requests in Allen County
- Coal project P55, Allen CountyCoal Β· 600 MW Β· withdrawn
- Coal project O44, Allen CountyCoal Β· 540 MW Β· withdrawn
- Birch SolarSolar Β· 300 MW Β· withdrawn
- Onshore wind project X3-031, Allen CountyOnshore wind Β· 150 MW Β· withdrawn
- Solar project AF1-076, Allen CountySolar Β· 100 MW Β· withdrawn
- Solar project AF1-077, Allen CountySolar Β· 100 MW Β· withdrawn
- Solar project X1-009, Allen CountySolar Β· 20.0 MW Β· withdrawn
- Battery storage project Z1-095, Allen CountyBattery storage Β· 6.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem