United States › Grid › Interconnection queues › Illinois

OCTARY USA · INTERCONNECTION QUEUES

Queue requests in study in Illinois — page 4

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown35863.7 GW
Active in queue74.6 GW423 requests
Agreement signed7,430 MW51 requests
Withdrawn670115.3 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

358 requests · page 4 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3519, Mason County
Onshore wind
200 MWIn study Mason, ILMISO Apr 2024target 2028
Battery storage project J3515, Sangamon County
Battery storage
200 MWIn study Sangamon, ILMISO Apr 2024target 2026
Battery storage project J2575, Tazewell County
Battery storage
198 MWIn study Tazewell, ILMISO Sep 2022target 2027
Onshore wind project J3566, Mclean County
Onshore wind
198 MWIn study Mclean, ILMISO Apr 2024target 2028
Onshore wind project J3753, Iroquois County
Onshore wind
196 MWIn study Iroquois, ILMISO Apr 2024target 2028
Solar project J3801, Mercer County
Solar
196 MWIn study Mercer, ILMISO Apr 2024target 2028
Solar project J2334, Montgomery County
Solar
195 MWIn study Montgomery, ILMISO Sep 2022target 2027
Solar project J3353, Champaign County
Solar
191 MWIn study Champaign, ILMISO Apr 2024target 2028
Gipper Wind Farm
Onshore wind · Gipper Wind Farm, LLC
191 MWIn study Whiteside, ILPJM Sep 2019target 2022
Solar project J2136, Iroquois County
Solar
191 MWIn study Iroquois, ILMISO Mar 2022target 2024
Battery storage project J3517, Williamson County
Battery storage
190 MWIn study Williamson, ILMISO Apr 2024target 2028
Solar project J3686, Christian County
Solar
190 MWIn study Christian, ILMISO Apr 2024target 2028
Surplus; AMIL.TILT1-4
Solar
188 MWIn study Vermilion, ILMISO May 2025target 2027
Solar project J2937, Montgomery County
Solar
186 MWIn study Montgomery, ILMISO Sep 2022target 2025
Solar project J2656, Macon County
Solar
180 MWIn study Macon, ILMISO Sep 2022target 2026
Solar + storage project J3003, Mason County
Solar + storage
180 MWIn study Mason, ILMISO Sep 2022target 2025
Solar project J1677, Macon County
Solar
180 MWIn study Macon, ILMISO Jun 2020target 2026
Solar project J3167, Fulton County
Solar
180 MWIn study Fulton, ILMISO Sep 2022target 2026
Solar project AH1-338, Lee County
Solar · Prairie Brome Solar LLC
180 MWIn study Lee, ILPJM Feb 2025target 2025
Solar project J3342, Vermilion County
Solar
180 MWIn study Vermilion, ILMISO Apr 2024target 2028
Onshore wind project J2247, Marshall County
Onshore wind
178 MWIn study Marshall, ILMISO Mar 2022target 2024
Solar project J2258, Adams County
Solar
175 MWIn study Adams, ILMISO Mar 2022target 2024
Solar + storage project J3254, Pulaski County
Solar + storage
175 MWIn study Pulaski, ILMISO Apr 2024target 2026
Solar project J3340, Vermilion County
Solar
175 MWIn study Vermilion, ILMISO Mar 2024target 2028
Onshore wind project J3905, Tazewell County
Onshore wind
175 MWIn study Tazewell, ILMISO Mar 2025target 2030
Solar + storage project J2273, Clinton County
Solar + storage
175 MWIn study Clinton, ILMISO Jul 2025target 2024
Solar + storage project J3732, Saline County
Solar + storage
175 MWIn study Saline, ILMISO Apr 2024target 2026
Battery storage project J3904, Tazewell County
Battery storage
175 MWIn study Tazewell, ILMISO Mar 2025target 2030
Solar + storage project J2266, Edgar County
Solar + storage
175 MWIn study Edgar, ILMISO Jun 2025target 2025
Nuclear project AH1-714, Lasalle County
Nuclear · Constellation Energy Generation, LLC
174 MWIn study Lasalle, ILPJM Apr 2025
Solar + storage project AH2-258, Kendall County
Solar + storage
172 MWIn study Kendall, ILPJM Mar 2022target 2024
Battery storage project AH2-259, Kendall County
Battery storage
172 MWIn study Kendall, ILPJM Mar 2022target 2024
Solar project J3382, Piatt County
Solar
171 MWIn study Piatt, ILMISO Apr 2024target 2028
Battery storage project AH2-204, Stephenson County
Battery storage
170 MWIn study Stephenson, ILPJM Mar 2022target 2026
Battery storage project AI1-156, Kane County
Battery storage
170 MWIn study Kane, ILPJM Sep 2022target 2027
Surplus; J291
Solar
169 MWIn study Scott, ILMISO Aug 2025target 2028
Solar project AI1-148, Kankakee County
Solar
164 MWIn study Kankakee, ILPJM Sep 2022target 2026
Solar project AH2-338, Winnebago County
Solar
160 MWIn study Winnebago, ILPJM Mar 2022target 2027
Solar + storage project AH1-543, Livingston County
Solar + storage · Golden Harvest Energy, LLC
157 MWIn study Livingston, ILPJM Feb 2025target 2025
Solar project J3064, Perry County
Solar
157 MWIn study Perry, ILMISO Sep 2022target 2026
Battery storage project AH2-376, Whiteside County
Battery storage
153 MWIn study Whiteside, ILPJM Mar 2022target 2027
Battery storage project AH2-377, Grundy County
Battery storage
150 MWIn study Grundy, ILPJM Mar 2022target 2024
Onshore wind project J1967, Champaign County
Onshore wind
150 MWIn study Champaign, ILMISO Mar 2022target 2025
Solar + storage project J2389, Adams County
Solar + storage
150 MWIn study Adams, ILMISO Sep 2022target 2026
Solar project J2659, Sangamon County
Solar
150 MWIn study Sangamon, ILMISO Oct 2025target 2026
Aurora Battery Storage II
Battery storage · Aurora Generation, LLC
150 MWIn study ILPJM Feb 2025target 2025
Bright Stalk Generating Facility
Onshore wind · Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2019target 2022
Solar project J2401, Johnson County
Solar
150 MWIn study Johnson, ILMISO Sep 2022target 2025
Leaf River Wind
Onshore wind · Leaf River Wind, LLC
150 MWIn study Ogle, ILPJM Sep 2018target 2021
Bright Stalk Generating Facility
Solar · Lexington Chenoa Wind Farm LLC
150 MWIn study Mclean, ILPJM Mar 2020target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)