United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in the USA — page 385

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown24,2054,519.8 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

24,205 requests · page 385 of 485
ProjectCapacityStatusLocationRegionQueuedOnline
Wagon Wheel MT. Solar 1
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Sep 2009target 2010
Onshore wind project 298, Owyhee County
Onshore wind
20.0 MWWithdrawn / abandoned Owyhee, IDWest Sep 2009
Solar project AH1-389, Warren County
Solar
20.0 MWWithdrawn / abandoned Warren, OHPJM Sep 2021target 2023
Solar project AF2-438, Mercer County
Solar
20.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2020target 2023
Five Forks Solar
Solar
20.0 MWWithdrawn / abandoned Warren, NCPJM Apr 2015target 2018
Onshore wind project 325, Twin Falls County
Onshore wind
20.0 MWWithdrawn / abandoned Twin Falls, IDWest Mar 2010
Bio Verde PV - Vander Woude
Solar
20.0 MWWithdrawn / abandoned Merced, CACAISO Feb 2010target 2012
Mantura II
Solar
20.0 MWWithdrawn / abandoned Surry, VAPJM Feb 2019target 2022
Desert Sun Ranch
Solar
20.0 MWWithdrawn / abandoned Los Angeles, CACAISO Dec 2010target 2013
Maricopa West Solar PV 3
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2017
Stonecrop
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Apr 2014target 2019
Cal SP V
Solar
20.0 MWWithdrawn / abandoned Merced, CACAISO Jan 2010target 2018
Solar project LGE-GIS-2021-026, Wise County
Solar
20.0 MWWithdrawn / abandoned Wise, VASoutheast Oct 2021target 2023
Coal project GI-0210, Mercer County
Coal
20.0 MWWithdrawn / abandoned Mercer, NDWest Jun 2002
Martin Rd Solar
Solar · Martin Rd Solar LLC
20.0 MWWithdrawn / abandoned Cattaraugus, NYNYISO Sep 2017
Solar project Q146, La Paz County
Solar
20.0 MWWithdrawn / abandoned La Paz, AZWest Jun 2010target 2011
Onshore wind project J283, Cottonwood County
Onshore wind
20.0 MWWithdrawn / abandoned Cottonwood, MNMISO May 2013
Solar
Solar
20.0 MWWithdrawn / abandoned York, MEISO-NE Jun 2024target 2028
Battery storage project AG2-381, Caroline County
Battery storage
20.0 MWWithdrawn / abandoned Caroline, MDPJM Mar 2021target 2023
CE-Shady Farm LLC
Solar
20.0 MWWithdrawn / abandoned Centre, PAPJM Mar 2019target 2025
Fairfax Solar Project
Solar
20.0 MWWithdrawn / abandoned Fresno, CACAISO Feb 2010target 2012
Solar project 451, Camas County
Solar
20.0 MWWithdrawn / abandoned Camas, IDWest Dec 2014
Solar project IC-639, Henry County
Solar
20.0 MWWithdrawn / abandoned Henry, ALSoutheast May 2017
Solar
Solar
20.0 MWWithdrawn / abandoned Berkshire, MAISO-NE Oct 2017target 2021
Evergreen Solar
Solar
20.0 MWWithdrawn / abandoned Elk, PAPJM Mar 2020target 2027
Pismo Solar
Solar
20.0 MWWithdrawn / abandoned San Luis Obispo, CACAISO Apr 2013target 2015
Round House Energy Storage
Battery storage
20.0 MWWithdrawn / abandoned San Mateo, CACAISO May 2016target 2020
Solar project AB2-086, City Of Chesapeake County
Solar
20.0 MWWithdrawn / abandoned City Of Chesapeake, VAPJM Apr 2016target 2017
Sun Hill Ranch Solar 1
Solar
20.0 MWWithdrawn / abandoned San Bernardino, CACAISO Mar 2011target 2016
Bradley BridgeSolar
Solar
20.0 MWWithdrawn / abandoned Chesterfield, VAPJM Mar 2019target 2025
Solar project IC-507, Henry County
Solar
20.0 MWWithdrawn / abandoned Henry, ALSoutheast Sep 2016
EX-Tidewater LLC
Solar
20.0 MWWithdrawn / abandoned Essex, VAPJM Sep 2020target 2027
Solar project AF2-344, Mercer County
Solar
20.0 MWWithdrawn / abandoned Mercer, PAPJM Mar 2020target 2023
Solar project J169, Jersey County
Solar
20.0 MWWithdrawn / abandoned Jersey, ILMISO Sep 2010target 2015
ELP Claverack Solar II LLC
Solar + storage · ELP Claverack Solar II LLC
20.0 MWWithdrawn / abandoned Columbia, NYNYISO Sep 2021
Cottontail Solar 3
Solar
20.0 MWWithdrawn / abandoned Montour, PAPJM Feb 2019target 2026
Battery storage project AE1-088, Beaufort County
Battery storage
20.0 MWWithdrawn / abandoned Beaufort, NCPJM Aug 2018target 2020
Solar project 1205, Crook County
Solar
20.0 MWWithdrawn / abandoned Crook, ORWest Apr 2020target 2023
Border Solar
Solar
20.0 MWWithdrawn / abandoned San Diego, CACAISO Apr 2013target 2015
Solar project Q122, Maricopa County
Solar
20.0 MWWithdrawn / abandoned Maricopa, AZWest Mar 2010target 2012
Allegany 2 Battery 2
Battery storage · Northland Power U.S. Projects
20.0 MWWithdrawn / abandoned Allegany, NYNYISO Jan 2021
Hosier Road Solar
Solar
20.0 MWWithdrawn / abandoned City Of Suffolk, VAPJM Mar 2019target 2022
Battery storage project AG1-451, Buckingham County
Battery storage · RWE Solar Development, LLC
20.0 MWWithdrawn / abandoned Buckingham, VAPJM Sep 2020target 2022
Solar project AG1-144, Clearfield County
Solar
20.0 MWWithdrawn / abandoned Clearfield, PAPJM Sep 2020target 2022
Battery storage project AA1-118, Pickaway County
Battery storage
20.0 MWWithdrawn / abandoned Pickaway, OHPJM Oct 2014target 2016
Carneras Solar 1
Solar
20.0 MWWithdrawn / abandoned Kern, CACAISO Apr 2015target 2018
Battery storage project AB1-147, Beaver County
Battery storage
20.0 MWWithdrawn / abandoned Beaver, PAPJM Oct 2015target 2016
Solar project AB2-089, Mecklenburg County
Solar
20.0 MWWithdrawn / abandoned Mecklenburg, VAPJM Apr 2016target 2017
Shaw Solar
Solar · Oya Solar NY LP
20.0 MWWithdrawn / abandoned Jefferson, NYNYISO Aug 2017
Pierce Brook - Lewis Run 230 kV
Solar · McKean County Solar, LLC
20.0 MWWithdrawn / abandoned Mckean, PANYISO Sep 2025
Page 385 of 485

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)