United States › Grid › Interconnection queues › Virginia
SOLAR · PJMHosier Road Solar
Hosier Road Solar is a 20.0 MW solar request withdrawn in the PJM interconnection queue, in City Of Suffolk County, Virginia, connecting to Dominion.
Queue statusWithdrawn / abandoned
- PlanningQueued Mar 2019 (completed)
- Withdrawn / abandonedApr 2021 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AE2-225
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- Dominion
- Connection point (POI)
- Suffolk 34 kV
- Location
- City Of Suffolk County, Virginia
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study; Interim/Interconnection Service Agreement: Wholesale Market P
- Queue status
- Withdrawn
- Entered queue
- 22 March 2019
- Proposed online date
- November 2022
- Withdrawn
- April 2021
Location
Marker shows the centre of City Of Suffolk County; the queue data does not give exact sites.
Other requests in City Of Suffolk County
- Battery storage project AI1-102, City Of Suffolk CountyBattery storage · 100 MW · in study
- Battery storage project AI1-089, City Of Suffolk CountyBattery storage · 100 MW · in study
- Battery storage project AH2-107, City Of Suffolk CountyBattery storage · 69.0 MW · in study
- Pleasant Hill SolarSolar · 20.0 MW · built
- Stratford Solar CenterSolar · 15.0 MW · built
- TWE Myrtle Solar ProjectSolar · 15.0 MW · built
- Battery storage project AH1-503, City Of Suffolk CountyBattery storage · 150 MW · withdrawn
- Solar + storage project AH1-613, City Of Suffolk CountySolar + storage · 130 MW · withdrawn
- Solar project AG1-027, City Of Suffolk CountySolar · 128 MW · withdrawn
- Solar project AG2-312, City Of Suffolk CountySolar · 125 MW · withdrawn
- Battery storage project AH1-323, City Of Suffolk CountyBattery storage · 100 MW · withdrawn
- Battery storage project AH1-730, City Of Suffolk CountyBattery storage · 100 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem