Cal SP V

Cal SP V is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Merced County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2010 (completed)
  2. Withdrawn / abandonedAug 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
550
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Merced #1 70 kV
Location
Merced County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
19 January 2010
Proposed online date
May 2018
Withdrawn
August 2016

Location

Marker shows the centre of Merced County; the queue data does not give exact sites.