United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· CAISO

Wagon Wheel MT. Solar 1

Wagon Wheel MT. Solar 1 is a 20.0 MW solar request withdrawn in the CAISO interconnection queue, in Kern County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2009 (completed)
  2. Withdrawn / abandonedDec 2010 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
525
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Arco Caneras 70kV line
Location
Kern County, California
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
11 September 2009
Proposed online date
December 2010
Withdrawn
December 2010

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem