πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί Illinois

SOLAR Β· MISO

Solar project J169, Jersey County

Solar project J169, Jersey County is a 20.0 MW solar request withdrawn in the MISO interconnection queue, in Jersey County, Illinois.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2010 (completed)
  2. Withdrawn / abandonedOct 2010 (project stopped here)
  3. ConsentedOct 2010 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J169
Grid region
MISO (Midcontinent)
Connection point (POI)
Ameren Jerseyville N.W. 138kV Substation
Location
Jersey County, Illinois
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
13 September 2010
Agreement signed
18 October 2010
Proposed online date
December 2015
Withdrawn
October 2010

Location

Marker shows the centre of Jersey County; the queue data does not give exact sites.

Power plants in Illinois Β· Transmission lines in Illinois

Other requests in Jersey County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem