BATTERY STORAGE · CAISO

Round House Energy Storage

Round House Energy Storage is a 20.0 MW battery storage request withdrawn in the CAISO interconnection queue, in San Mateo County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued May 2016 (completed)
  2. Withdrawn / abandonedJul 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1280
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
PG&E Martin Substation 115kV
Location
San Mateo County, California
Technology
Battery: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
2 May 2016
Proposed online date
June 2020
Withdrawn
July 2016

Location

Marker shows the centre of San Mateo County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in San Mateo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem